Withdrawn queue requests in the USA (2017 requests) โ€” page 24

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,258161.7 GW
Active in queue51.0 GW292 requests
Agreement signed32.8 GW182 requests
Withdrawn1,258161.7 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,258 requests ยท page 24 of 26
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 946, Deschutes County
Solar
9.0 MWWithdrawn / abandoned Deschutes, ORWest Sep 2017target 2019
Solar project SGI-PNM-2017-03, Santa Fe County
Solar
9.0 MWWithdrawn / abandoned Santa Fe, NMWest Mar 2017target 2018
Solar project GEN-2017-103, Chippewa County
Solar
8.0 MWWithdrawn / abandoned Chippewa, MNSPP May 2017target 2018
CHP
Gas
8.0 MWWithdrawn / abandoned Coos, NHISO-NE Apr 2017target 2018
Onshore wind project 857, Columbia County
Onshore wind
7.8 MWWithdrawn / abandoned Columbia, WAWest Mar 2017target 2019
Solar project AD2-007, Surry County
Solar
7.6 MWWithdrawn / abandoned Surry, VAPJM Nov 2017target 2019
Gas project AD1-019, Atlantic County
Gas
7.6 MWWithdrawn / abandoned Atlantic, NJPJM May 2017target 2019
Solar project SGI-PNM-2017-02, Luna County
Solar
7.5 MWWithdrawn / abandoned Luna, NMWest Jan 2017target 2018
Riverhead
Solar ยท Hecate Energy Riverhead, LLC
7.5 MWWithdrawn / abandoned Suffolk, NYNYISO Feb 2017
Solar project AD2-006, Hunterdon County
Solar
7.5 MWWithdrawn / abandoned Hunterdon, NJPJM Nov 2017target 2018
Yaphank Solid Waste Management
Battery storage ยท Yaphank Fuel Cell Park, LLC
7.4 MWWithdrawn / abandoned Suffolk, NYNYISO Aug 2017
Liberty Dr
Solar ยท Solar Liberty Energy Systems, Inc.
7.4 MWWithdrawn / abandoned Niagara, NYNYISO Sep 2017
Solar
Solar
7.0 MWWithdrawn / abandoned Washington, RIISO-NE Nov 2017target 2020
Solar project AD1-030, Burlington County
Solar
7.0 MWWithdrawn / abandoned Burlington, NJPJM Jul 2017target 2018
Gas project GI-2017-22, Weld County
Gas
6.4 MWWithdrawn / abandoned Weld, COWest Jul 2017target 2018
Solar
Solar
6.1 MWWithdrawn / abandoned Washington, RIISO-NE Nov 2017target 2020
Solar project 897, Klamath County
Solar
6.0 MWWithdrawn / abandoned Klamath, ORWest Jun 2017target 2019
Solar project 911, Deschutes County
Solar
5.5 MWWithdrawn / abandoned Deschutes, ORWest Jul 2017target 2019
Solar project 961, Washakie County
Solar
5.0 MWWithdrawn / abandoned Washakie, WYWest Oct 2017target 2019
Battery storage project G0567, Douglas County
Battery storage
5.0 MWWithdrawn / abandoned Douglas, WAWest Jun 2017target 2019
Solar project 17-09112, Larimer County
Solar
5.0 MWWithdrawn / abandoned Larimer, COWest Sep 2017target 2018
Solar project 960, Uinta County
Solar
5.0 MWWithdrawn / abandoned Uinta, WYWest Oct 2017target 2019
Solar project 959, Albany County
Solar
5.0 MWWithdrawn / abandoned Albany, WYWest Oct 2017target 2019
Solar project 17-09111, Larimer County
Solar
5.0 MWWithdrawn / abandoned Larimer, COWest Sep 2017target 2018
Other project AD1-111, Clinton County
Other
4.1 MWWithdrawn / abandoned Clinton, PAPJM Sep 2017target 2018
Solar project AC2-169, Gloucester County
Solar
4.1 MWWithdrawn / abandoned Gloucester, NJPJM Mar 2017target 2017
Onshore wind project 334, Lewis And Clark County
Onshore wind
4.0 MWWithdrawn / abandoned Lewis And Clark, MTWest Sep 2017target 2019
Solar project 896, Marion County
Solar
4.0 MWWithdrawn / abandoned Marion, ORWest Jun 2017target 2018
Solar project 913, Marion County
Solar
4.0 MWWithdrawn / abandoned Marion, ORWest Jul 2017target 2018
Solar project 878, Wallowa County
Solar
4.0 MWWithdrawn / abandoned Wallowa, ORWest May 2017target 2018
Offshore wind project AD1-089, City Of Virginia Beach County
Offshore wind
4.0 MWWithdrawn / abandoned City Of Virginia Beach, VAPJM Sep 2017target 2020
Hood Cogen
Gas ยท HP Hood LLC
4.0 MWWithdrawn / abandoned Madison, NYNYISO Jan 2017
Onshore wind project 318, Meagher County
Onshore wind
3.3 MWWithdrawn / abandoned Meagher, MTWest Jun 2017target 2018
Onshore wind project 319, Meagher County
Onshore wind
3.3 MWWithdrawn / abandoned Meagher, MTWest Jun 2017target 2018
Onshore wind project 320, Meagher County
Onshore wind
3.3 MWWithdrawn / abandoned Meagher, MTWest Jun 2017target 2018
Solar project 910, Jackson County
Solar
3.0 MWWithdrawn / abandoned Jackson, ORWest Jul 2017target 2019
Other project AC2-099, Lake County
Other
3.0 MWWithdrawn / abandoned Lake, OHPJM Mar 2017target 2018
Solar project 945, Linn County
Solar
3.0 MWWithdrawn / abandoned Linn, ORWest Sep 2017target 2018
Solar project 520, Malheur County
Solar
3.0 MWWithdrawn / abandoned Malheur, ORWest Jan 2017
Solar project 984, Polk County
Solar
3.0 MWWithdrawn / abandoned Polk, ORWest Nov 2017target 2019
Solar project 943, Marion County
Solar
3.0 MWWithdrawn / abandoned Marion, ORWest Sep 2017target 2018
Solar project AC2-143, Middlesex County
Solar
3.0 MWWithdrawn / abandoned Middlesex, NJPJM Mar 2017target 2019
Solar project 329, Chouteau County
Solar
3.0 MWWithdrawn / abandoned Chouteau, MTWest Aug 2017target 2018
Solar project 332, Teton County
Solar
3.0 MWWithdrawn / abandoned Teton, MTWest Aug 2017target 2018
Solar project 331, Pondera County
Solar
3.0 MWWithdrawn / abandoned Pondera, MTWest Aug 2017target 2018
Plainsboro 13kV
Solar
3.0 MWWithdrawn / abandoned Middlesex, NJPJM Aug 2017target 2018
Solar project 942, Marion County
Solar
3.0 MWWithdrawn / abandoned Marion, ORWest Sep 2017target 2018
Solar project 983, Klamath County
Solar
3.0 MWWithdrawn / abandoned Klamath, ORWest Nov 2017target 2019
Solar project 914, Klamath County
Solar
3.0 MWWithdrawn / abandoned Klamath, ORWest Jul 2017target 2018
Solar project 912, Marion County
Solar
3.0 MWWithdrawn / abandoned Marion, ORWest Jul 2017target 2018

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)