United States β€Ί Grid β€Ί Interconnection queues β€Ί Wyoming

SOLAR Β· WEST

Solar project 960, Uinta County

Solar project 960, Uinta County is a 5.0 MW solar request withdrawn in the West interconnection queue, in Uinta County, Wyoming, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2017 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
960
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Circuit EVA14 out of Evanston substation
Location
Uinta County, Wyoming
Technology
Solar: 5.0 MW
Total requested
5.0 MW
Service type
Network resource (NRIS)
Study phase
WITHDRAWN BY CUSTOMER
Queue status
Withdrawn
Entered queue
13 October 2017
Proposed online date
May 2019

Location

Marker shows the centre of Uinta County; the queue data does not give exact sites.

Power plants in Wyoming Β· Transmission lines in Wyoming

Other requests in Uinta County