United States β€Ί Grid β€Ί Interconnection queues β€Ί Wyoming

ONSHORE WIND Β· WEST

Onshore wind project C2-63, Uinta County

Onshore wind project C2-63, Uinta County is a 220 MW onshore wind request withdrawn in the West interconnection queue, in Uinta County, Wyoming, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
C2-63
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Railroad substation
Location
Uinta County, Wyoming
Technology
Wind: 220 MW
Total requested
220 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
10 May 2022
Proposed online date
September 2026

Location

Marker shows the centre of Uinta County; the queue data does not give exact sites.

Power plants in Wyoming Β· Transmission lines in Wyoming

Other requests in Uinta County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem