Requests shown64684.7 GW
Active in queue33.8 GW154 requests
Agreement signed4,095 MW25 requests
Withdrawn64684.7 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

646 requests · page 2 of 13
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 246, Salt Lake County
Gas
380 MWWithdrawn / abandoned Salt Lake, UTWest Nov 2008target 2012
Gas project 308, Salt Lake County
Gas · Parowan Solar Energy, LLC
380 MWWithdrawn / abandoned Salt Lake, UTWest Dec 2009target 2014
Gas project 244, Weber County
Gas
380 MWWithdrawn / abandoned Weber, UTWest Nov 2008target 2012
Gas project 245, Salt Lake County
Gas
380 MWWithdrawn / abandoned Salt Lake, UTWest Nov 2008target 2012
Solar project 772, Iron County
Solar
375 MWWithdrawn / abandoned Iron, UTWest Jul 2016target 2018
Onshore wind project 300, Rich County
Onshore wind
362 MWWithdrawn / abandoned Rich, UTWest Oct 2009target 2013
Solar + storage project 1225, Juab County
Solar + storage
350 MWWithdrawn / abandoned Juab, UTWest Apr 2020target 2023
Solar + storage project C2-142, Utah County
Solar + storage
325 MWWithdrawn / abandoned Utah, UTWest May 2022target 2025
Gas project 224-A, Juab County
Gas · PacifiCorp Commercial & Trading
320 MWWithdrawn / abandoned Juab, UTWest May 2008target 2012
Gas project 37, Utah County
Gas
310 MWWithdrawn / abandoned Utah, UTWest Jan 2004target 2006
Battery storage project C3-167, San Juan County
Battery storage
300 MWWithdrawn / abandoned San Juan, UTWest May 2023target 2026
Battery storage project C2-16, Carbon County
Battery storage · PacifiCorp
300 MWWithdrawn / abandoned Carbon, UTWest Apr 2022target 2028
Solar + storage project C1-47, Iron County
Solar + storage
300 MWWithdrawn / abandoned Iron, UTWest May 2021target 2025
Solar + storage project C3-133, Box Elder County
Solar + storage
300 MWWithdrawn / abandoned Box Elder, UTWest May 2023target 2027
Onshore wind project PIS029, Utah County
Onshore wind
300 MWWithdrawn / abandoned Utah, UTWest Mar 2023target 2027
Solar + storage project C4-111, Iron County
Solar + storage
300 MWWithdrawn / abandoned Iron, UTWest May 2024target 2029
Solar + storage project C4-043, Sanpete County
Solar + storage
300 MWWithdrawn / abandoned Sanpete, UTWest May 2024target 2029
Solar + storage project 982, Utah County
Solar + storage
300 MWWithdrawn / abandoned Utah, UTWest Nov 2017target 2020
Battery storage project C2-97, Salt Lake County
Battery storage
300 MWWithdrawn / abandoned Salt Lake, UTWest May 2022target 2025
Gas project PIS041, Utah County
Gas
300 MWWithdrawn / abandoned Utah, UTWest Jun 2023target 2026
Solar + storage project C2-36, Utah County
Solar + storage
300 MWWithdrawn / abandoned Utah, UTWest Apr 2022target 2025
Solar + storage project C3-124, Juab County
Solar + storage
300 MWWithdrawn / abandoned Juab, UTWest May 2023target 2027
Solar project 1049, Utah County
Solar
300 MWWithdrawn / abandoned Utah, UTWest Jul 2018target 2020
Solar project 1050, Utah County
Solar
300 MWWithdrawn / abandoned Utah, UTWest Jul 2018target 2020
Battery storage project C3-045, Box Elder County
Battery storage · PacifiCorp
300 MWWithdrawn / abandoned Box Elder, UTWest May 2023target 2030
Solar + storage project C3-142, Tooele County
Solar + storage
300 MWWithdrawn / abandoned Tooele, UTWest May 2023target 2028
Solar + storage project C3-101, Millard County
Solar + storage
300 MWWithdrawn / abandoned Millard, UTWest May 2023target 2026
Solar + storage project C3-034, Utah County
Solar + storage
300 MWWithdrawn / abandoned Utah, UTWest May 2023target 2026
Gas project C3-053, Utah County
Gas
300 MWWithdrawn / abandoned Utah, UTWest May 2023target 2025
Solar project 1202, San Juan County
Solar
300 MWWithdrawn / abandoned San Juan, UTWest Mar 2020target 2022
Gas project 223, Salt Lake County
Gas
300 MWWithdrawn / abandoned Salt Lake, UTWest May 2008target 2011
Solar + storage project 985, Utah County
Solar + storage
300 MWWithdrawn / abandoned Utah, UTWest Nov 2017target 2020
Solar + storage project C4-040, Millard County
Solar + storage
300 MWWithdrawn / abandoned Millard, UTWest May 2024target 2027
Solar + storage project PIS048, Utah County
Solar + storage
300 MWWithdrawn / abandoned Utah, UTWest Dec 2023target 2026
Solar project 997, Iron County
Solar
300 MWWithdrawn / abandoned Iron, UTWest Dec 2017target 2020
Solar + storage project PIS035, Washington County
Solar + storage
300 MWWithdrawn / abandoned Washington, UTWest May 2023target 2026
Solar + storage project C2-75, Tooele County
Solar + storage
300 MWWithdrawn / abandoned Tooele, UTWest May 2022target 2027
Gas project 359, Salt Lake County
Gas
275 MWWithdrawn / abandoned Salt Lake, UTWest Nov 2010target 2014
Solar + storage project C3-027, Juab County
Solar + storage
275 MWWithdrawn / abandoned Juab, UTWest May 2023target 2026
Solar + storage project C2-37, Juab County
Solar + storage
275 MWWithdrawn / abandoned Juab, UTWest Apr 2022target 2025
Gas project 377, Salt Lake County
Gas
275 MWWithdrawn / abandoned Salt Lake, UTWest Mar 2011target 2014
Coal project 121, Sevier County
Coal · PacifiCorp Commercial & Trading
270 MWWithdrawn / abandoned Sevier, UTWest Feb 2007target 2009
Gas project C3-107, Utah County
Gas
260 MWWithdrawn / abandoned Utah, UTWest May 2023target 2026
Solar + storage project 1027, Tooele County
Solar + storage
251 MWWithdrawn / abandoned Tooele, UTWest May 2018target 2022
Solar + storage project 1028, Tooele County
Solar + storage
251 MWWithdrawn / abandoned Tooele, UTWest May 2018target 2022
Solar + storage project C3-018, Juab County
Solar + storage
250 MWWithdrawn / abandoned Juab, UTWest Apr 2023target 2025
Solar + storage project C3-028, Iron County
Solar + storage
250 MWWithdrawn / abandoned Iron, UTWest May 2023target 2027
Solar + storage project 1224, San Juan County
Solar + storage
250 MWWithdrawn / abandoned San Juan, UTWest Apr 2020target 2023
Solar + storage project 1100, Emery County
Solar + storage
250 MWWithdrawn / abandoned Emery, UTWest Jan 2019target 2021
Battery storage project C4-048, Salt Lake County
Battery storage
250 MWWithdrawn / abandoned Salt Lake, UTWest May 2024target 2027
Page 2 of 13

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20102025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)