United States › Grid › Interconnection queues › Pennsylvania

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Pennsylvania — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,354164.3 GW
Active in queue12.5 GW231 requests
Agreement signed2,306 MW58 requests
Withdrawn1,354164.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,354 requests · page 2 of 28
ProjectCapacityStatusLocationRegionQueuedOnline
Coal project Q89, Schuylkill County
Coal
750 MWWithdrawn / abandoned Schuylkill, PAPJM Jul 2006target 2012
Gas project G41, Bucks County
Gas
750 MWWithdrawn / abandoned Bucks, PAPJM Jul 2001
Gas project Y3-098, Delaware County
Gas
735 MWWithdrawn / abandoned Delaware, PAPJM Apr 2013target 2017
Gas project U3-023, Delaware County
Gas
720 MWWithdrawn / abandoned Delaware, PAPJM Oct 2008target 2012
Gas project U1-015, Montgomery County
Gas
700 MWWithdrawn / abandoned Montgomery, PAPJM Feb 2008target 2013
Gas project U1-014, Montgomery County
Gas
700 MWWithdrawn / abandoned Montgomery, PAPJM Feb 2008target 2013
Gas project U4-005, Luzerne County
Gas
700 MWWithdrawn / abandoned Luzerne, PAPJM Nov 2008target 2013
Coal project T128, Fayette County
Coal
700 MWWithdrawn / abandoned Fayette, PAPJM Jan 2008target 2012
Gas project U2-099, Northampton County
Gas
700 MWWithdrawn / abandoned Northampton, PAPJM Jul 2008target 2014
Gas project U1-016, Lancaster County
Gas
700 MWWithdrawn / abandoned Lancaster, PAPJM Feb 2008target 2013
Gas project A60, Adams County
Gas
679 MWWithdrawn / abandoned Adams, PAPJM Apr 1999
Gas project X3-068, York County
Gas
678 MWWithdrawn / abandoned York, PAPJM Oct 2011target 2017
Gas project G32, York County
Gas
675 MWWithdrawn / abandoned York, PAPJM May 2001target 2005
Gas project Z2-064, Washington County
Gas
651 MWWithdrawn / abandoned Washington, PAPJM Apr 2014target 2018
Gas project U2-074, Lancaster County
Gas
650 MWWithdrawn / abandoned Lancaster, PAPJM Jul 2008target 2012
Gas project V4-020, Berks County
Gas
650 MWWithdrawn / abandoned Berks, PAPJM Nov 2009target 2016
Gas project F05, Armstrong County
Gas
646 MWWithdrawn / abandoned Armstrong, PAPJM Jan 2001
Gas project E17_W29, Westmoreland County
Gas
640 MWWithdrawn / abandoned Westmoreland, PAPJM Nov 2000target 2005
Gas project AH1-733, Luzerne County
Gas · Invenergy Energy Transition LLC
638 MWWithdrawn / abandoned Luzerne, PAPJM target 2031
Gas project U2-075, Lackawanna County
Gas
636 MWWithdrawn / abandoned Lackawanna, PAPJM Jul 2008target 2012
Gas project H09, Somerset County
Gas
635 MWWithdrawn / abandoned Somerset, PAPJM Nov 2001target 2006
Gas project U1-013, Delaware County
Gas
630 MWWithdrawn / abandoned Delaware, PAPJM Feb 2008target 2013
Gas project U1-012, Philadelphia County
Gas
630 MWWithdrawn / abandoned Philadelphia, PAPJM Feb 2008target 2013
Gas project AF1-235, Snyder County
Gas
617 MWWithdrawn / abandoned Snyder, PAPJM Sep 2019target 2023
Gas project A27, Philadelphia County
Gas
615 MWWithdrawn / abandoned Philadelphia, PAPJM Nov 1998
Gas project G14, Lancaster County
Gas
610 MWWithdrawn / abandoned Lancaster, PAPJM Mar 2001target 2004
Gas project G31, Indiana County
Gas
610 MWWithdrawn / abandoned Indiana, PAPJM May 2001target 2005
Gas project G13, Bucks County
Gas
600 MWWithdrawn / abandoned Bucks, PAPJM Mar 2001target 2005
Gas project G42, Indiana County
Gas
600 MWWithdrawn / abandoned Indiana, PAPJM Jul 2001target 2004
Gas project G43, Indiana County
Gas
600 MWWithdrawn / abandoned Indiana, PAPJM Jul 2001
Gas project B10, Armstrong County
Gas
600 MWWithdrawn / abandoned Armstrong, PAPJM Jun 1999
Gas project B31, Lancaster County
Gas
600 MWWithdrawn / abandoned Lancaster, PAPJM Nov 1999
Other project U3-009, Northampton County
Other
595 MWWithdrawn / abandoned Northampton, PAPJM Aug 2008target 2014
Coal project V1-013, Allegheny County
Coal
580 MWWithdrawn / abandoned Allegheny, PAPJM Feb 2009target 2012
Other project AE1-234, Chester County
Other
578 MWWithdrawn / abandoned Chester, PAPJM Sep 2018
Gas project V4-002, York County
Gas
575 MWWithdrawn / abandoned York, PAPJM Nov 2009target 2014
Gas project G45, Philadelphia County
Gas
575 MWWithdrawn / abandoned Philadelphia, PAPJM Jul 2001target 2005
Gas project H24, Elk County
Gas
575 MWWithdrawn / abandoned Elk, PAPJM Jan 2002target 2006
Gas project AB1-151, Wayne County
Gas
575 MWWithdrawn / abandoned Wayne, PAPJM Oct 2015target 2020
Gas project H10, Berks County
Gas
560 MWWithdrawn / abandoned Berks, PAPJM Nov 2001target 2005
Gas project H08, Philadelphia County
Gas
560 MWWithdrawn / abandoned Philadelphia, PAPJM Nov 2001target 2005
Gas project B45, Lackawanna County
Gas
555 MWWithdrawn / abandoned Lackawanna, PAPJM Nov 1999target 2004
Gas project F01, Dauphin County
Gas
551 MWWithdrawn / abandoned Dauphin, PAPJM Dec 2000target 2004
Gas project D19, Lancaster County
Gas
550 MWWithdrawn / abandoned Lancaster, PAPJM Jul 2000target 2004
Gas project L06, York County
Gas
550 MWWithdrawn / abandoned York, PAPJM Oct 2003target 2006
Gas project D20, Lancaster County
Gas
550 MWWithdrawn / abandoned Lancaster, PAPJM Jul 2000target 2005
Gas project D28, Philadelphia County
Gas
550 MWWithdrawn / abandoned Philadelphia, PAPJM Jul 2000
Gas project C14, Indiana County
Gas
550 MWWithdrawn / abandoned Indiana, PAPJM Mar 2000
Gas project P05, York County
Gas
550 MWWithdrawn / abandoned York, PAPJM Sep 2005target 2008
Gas project D16, Dauphin County
Gas
550 MWWithdrawn / abandoned Dauphin, PAPJM Jul 2000
Page 2 of 28

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)