United States › Grid › Interconnection queues › Oregon
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in Oregon — page 2
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Battery storage project G0949, Gilliam County Battery storage |
650 MW | Withdrawn / abandoned |
| Solar project G0785, Morrow County Solar |
650 MW | Withdrawn / abandoned |
| Battery storage project G0961, Umatilla County Battery storage |
650 MW | Withdrawn / abandoned |
| Battery storage project G1049, Harney County Battery storage |
650 MW | Withdrawn / abandoned |
| Solar project G0649, Wasco County Solar |
641 MW | Withdrawn / abandoned |
| Duke Energy NA Gas · Duke Energy North America, LLC |
640 MW | Withdrawn / abandoned |
| Solar + storage project C4-026, Harney County Solar + storage |
640 MW | Withdrawn / abandoned |
| National Energy and Gas Tx Gas · National Energy & Gas Transmission, Inc. |
620 MW | Withdrawn / abandoned |
| Sempra Generation Gas · Sempra Generation, LLC |
612 MW | Withdrawn / abandoned |
| Solar + storage project G0755, Klamath County Solar + storage |
600 MW | Withdrawn / abandoned |
| Solar project 1040, Lake County Solar |
600 MW | Withdrawn / abandoned |
| Onshore wind project G0306, Harney County Onshore wind |
600 MW | Withdrawn / abandoned |
| Battery storage project G0784, Wasco County Battery storage |
600 MW | Withdrawn / abandoned |
| Solar + storage project G0813, Umatilla County Solar + storage |
600 MW | Withdrawn / abandoned |
| Peoples Energy Resources Geothermal · Peoples Energy Resources Corporation |
600 MW | Withdrawn / abandoned |
| Solar project 1064, Crook County Solar |
600 MW | Withdrawn / abandoned |
| Battery storage project G0776, Wasco County Battery storage |
600 MW | Withdrawn / abandoned |
| Battery storage project G0780, Wasco County Battery storage |
600 MW | Withdrawn / abandoned |
| Battery storage project G0788, Wasco County Battery storage |
600 MW | Withdrawn / abandoned |
| Solar project G0783, Wasco County Solar |
600 MW | Withdrawn / abandoned |
| Solar + storage project G1061, Jefferson County Solar + storage |
600 MW | Withdrawn / abandoned |
| Solar + storage project G0662, Deschutes County Solar + storage |
600 MW | Withdrawn / abandoned |
| Duke Energy NA Gas · Duke Energy North America, LLC |
600 MW | Withdrawn / abandoned |
| Gas project G0530, Morrow County Gas |
600 MW | Withdrawn / abandoned |
| Solar project G0590, Lake County Solar |
600 MW | Withdrawn / abandoned |
| Solar + storage project C3-180, Morrow County Solar + storage |
600 MW | Withdrawn / abandoned |
| Battery storage project G0809, Douglas County Battery storage |
600 MW | Withdrawn / abandoned |
| Hydro project 509, Klamath County Hydro · CBG Portland, LLC |
600 MW | Withdrawn / abandoned |
| Solar + storage project 1093, Crook County Solar + storage |
600 MW | Withdrawn / abandoned |
| Onshore wind project 343, Morrow County Onshore wind |
600 MW | Withdrawn / abandoned |
| Solar project G0674, Crook County Solar |
600 MW | Withdrawn / abandoned |
| Solar + storage project PIS044, Morrow County Solar + storage |
600 MW | Withdrawn / abandoned |
| Solar + storage project G0939, Gilliam County Solar + storage |
600 MW | Withdrawn / abandoned |
| Solar + storage project 22-119, Lake County Solar + storage |
600 MW | Withdrawn / abandoned |
| Solar project 18-071, Lake County Solar |
600 MW | Withdrawn / abandoned |
| Solar + storage project 1165, Crook County Solar + storage |
600 MW | Withdrawn / abandoned |
| Battery storage project G0725, Coos County Battery storage |
600 MW | Withdrawn / abandoned |
| Onshore wind project 346, Umatilla County Onshore wind |
599 MW | Withdrawn / abandoned |
| PG and E Generation Gas |
581 MW | Withdrawn / abandoned |
| Coburg Power Gas · Coberg Power LLC |
570 MW | Withdrawn / abandoned |
| Solar + storage project 22-113, Lake County Solar + storage |
560 MW | Withdrawn / abandoned |
| Summit/Westward Gas · Summit Power Northwest Project, LLC |
536 MW | Withdrawn / abandoned |
| Summit PNW Gas · Summit Power Northwest Project, LLC |
520 MW | Withdrawn / abandoned |
| Solar + storage project 23-236, Jefferson County Solar + storage |
513 MW | Withdrawn / abandoned |
| Solar + storage project 23-235, Jefferson County Solar + storage |
513 MW | Withdrawn / abandoned |
| Onshore wind project 289, Lake County Onshore wind · Ridgeline Energy, LLC |
501 MW | Withdrawn / abandoned |
| Solar + storage project C4-011, Morrow County Solar + storage |
500 MW | Withdrawn / abandoned |
| Onshore wind project G0462, Lake County Onshore wind |
500 MW | Withdrawn / abandoned |
| Battery storage project C3-069, Lake County Battery storage · PacifiCorp |
500 MW | Withdrawn / abandoned |
| Battery storage project C2-18, Klamath County Battery storage · PacifiCorp |
500 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)