United States βΊ Grid βΊ Interconnection queues βΊ Michigan
OCTARY USA Β· INTERCONNECTION QUEUESInterconnection queue in Michigan (2022 requests) β page 2
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project J2484, Monroe County Solar |
100 MW | In study |
| Battery storage project J3007, Mason County Battery storage |
100 MW | In study |
| Surplus; Polaris Solar Other |
100 MW | Agreement signed |
| Battery storage project J2618, Macomb County Battery storage |
100 MW | In study |
| Solar + storage project AH2-418, Berrien County Solar + storage |
100 MW | In study |
| Battery storage project J2392, Mason County Battery storage |
100 MW | In study |
| Battery storage project J2499, Ottawa County Battery storage |
100 MW | In study |
| Solar project J2679, Livingston County Solar |
100 MW | In study |
| Surplus; J728 Other |
90.0 MW | In study |
| Surplus; J717 Other |
90.0 MW | In study |
| Solar project J2874, Bay County Solar |
85.0 MW | In study |
| Surplus; Pine River Solar Other |
80.0 MW | Agreement signed |
| Surplus; J928 Other |
55.0 MW | In study |
| Solar project J3066, Osceola County Solar |
50.0 MW | In study |
| Solar project J3065, Oceana County Solar |
20.0 MW | In study |
| Gas project J2969, Kalkaska County Gas |
13.4 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)