United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Michigan (2022 requests) β€” page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6610.6 GW
Active in queue10.6 GW66 requests
Agreement signed180 MW2 requests
Withdrawn314,138 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

66 requests Β· page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J2484, Monroe County
Solar
100 MWIn study Monroe, MIMISO Sep 2022target 2025
Battery storage project J3007, Mason County
Battery storage
100 MWIn study Mason, MIMISO Aug 2022target 2025
Surplus; Polaris Solar
Other
100 MWAgreement signed Gratiot, MIMISO Apr 2022target 2023
Battery storage project J2618, Macomb County
Battery storage
100 MWIn study Macomb, MIMISO Sep 2022target 2026
Solar + storage project AH2-418, Berrien County
Solar + storage
100 MWIn study Berrien, MIPJM Mar 2022target 2026
Battery storage project J2392, Mason County
Battery storage
100 MWIn study Mason, MIMISO Sep 2022target 2026
Battery storage project J2499, Ottawa County
Battery storage
100 MWIn study Ottawa, MIMISO Sep 2022target 2026
Solar project J2679, Livingston County
Solar
100 MWIn study Livingston, MIMISO Sep 2022target 2027
Surplus; J728
Other
90.0 MWIn study Isabella, MIMISO Aug 2022target 2025
Surplus; J717
Other
90.0 MWIn study Isabella, MIMISO Aug 2022target 2025
Solar project J2874, Bay County
Solar
85.0 MWIn study Bay, MIMISO Aug 2022target 2025
Surplus; Pine River Solar
Other
80.0 MWAgreement signed Gratiot, MIMISO Apr 2022target 2023
Surplus; J928
Other
55.0 MWIn study Delta, MIMISO Apr 2022target 2025
Solar project J3066, Osceola County
Solar
50.0 MWIn study Osceola, MIMISO Sep 2022target 2026
Solar project J3065, Oceana County
Solar
20.0 MWIn study Oceana, MIMISO Sep 2022target 2025
Gas project J2969, Kalkaska County
Gas
13.4 MWIn study Kalkaska, MIMISO Sep 2022target 2002
Page 2 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)