FERMI Storage Project Battery storage · DTE Electric |
248 MW | In study |
Monroe, MI | MISO |
Aug 2025 | target 2028 |
Solar project J3945, Washtenaw County Solar |
245 MW | In study |
Washtenaw, MI | MISO |
Apr 2025 | target 2030 |
Battery storage project J2567, Oceana County Battery storage |
240 MW | In study |
Oceana, MI | MISO |
Sep 2022 | target 2025 |
Onshore wind project J3864, Shiawassee County Onshore wind |
230 MW | In study |
Shiawassee, MI | MISO |
Dec 2024 | target 2028 |
Solar project J2673, Clare County Solar |
225 MW | In study |
Clare, MI | MISO |
Sep 2022 | target 2025 |
Solar project J3838, Ingham County Solar |
225 MW | In study |
Ingham, MI | MISO |
Apr 2024 | target 2028 |
Solar project J2668, Mason County Solar |
225 MW | In study |
Mason, MI | MISO |
Sep 2022 | target 2025 |
Battery storage project J3696, Montcalm County Battery storage |
225 MW | In study |
Montcalm, MI | MISO |
Apr 2024 | target 2026 |
Solar project J2670, Mason County Solar |
223 MW | In study |
Mason, MI | MISO |
Sep 2022 | target 2025 |
Onshore wind project J3496, Sanilac County Onshore wind |
220 MW | In study |
Sanilac, MI | MISO |
Apr 2024 | target 2027 |
Solar project J2444, Van Buren County Solar |
220 MW | In study |
Van Buren, MI | MISO |
Sep 2022 | target 2026 |
Replacing 220 MW of coal generation with BESS; Trenton Channel 9 Other |
220 MW | In study |
Wayne, MI | MISO |
Oct 2023 | target 2025 |
Battery storage project J3646, St. Clair County Battery storage |
220 MW | In study |
St. Clair, MI | MISO |
Apr 2024 | target 2028 |
Solar project J2001, Newaygo County Solar |
220 MW | In study |
Newaygo, MI | MISO |
Aug 2021 | target 2025 |
Solar project J2814, Kalamazoo County Solar |
220 MW | In study |
Kalamazoo, MI | MISO |
Sep 2022 | target 2026 |
Solar project J2611, Alcona County Solar |
215 MW | In study |
Alcona, MI | MISO |
Sep 2022 | target 2028 |
Solar project J3940, Isabella County Solar |
214 MW | In study |
Isabella, MI | MISO |
Feb 2025 | target 2030 |
Deckerville Solar Park Project Solar · DTE Electric |
213 MW | In study |
Sanilac, MI | MISO |
Aug 2025 | target 2028 |
Solar project J2878, Sanilac County Solar |
200 MW | In study |
Sanilac, MI | MISO |
Sep 2022 | target 2025 |
Battery storage project J2991, Wayne County Battery storage |
200 MW | In study |
Wayne, MI | MISO |
Sep 2022 | target 2025 |
Solar project J2061, Saginaw County Solar |
200 MW | In study |
Saginaw, MI | MISO |
Aug 2021 | target 2024 |
Battery storage project J2799, Van Buren County Battery storage |
200 MW | In study |
Van Buren, MI | MISO |
Oct 2025 | target 2025 |
Solar project J3545, Ionia County Solar |
200 MW | In study |
Ionia, MI | MISO |
Apr 2024 | target 2028 |
Solar project J3472, Lapeer County Solar |
200 MW | In study |
Lapeer, MI | MISO |
Apr 2024 | target 2028 |
Solar project J2672, Shiawassee County Solar |
200 MW | In study |
Shiawassee, MI | MISO |
Sep 2022 | target 2025 |
Solar project J2877, Midland County Solar |
200 MW | In study |
Midland, MI | MISO |
Sep 2022 | target 2025 |
Solar project J3859, Branch County Solar |
200 MW | In study |
Branch, MI | MISO |
Dec 2024 | target 2028 |
Battery storage project J2889, Allegan County Battery storage |
200 MW | In study |
Allegan, MI | MISO |
Sep 2022 | target 2025 |
Battery storage project J2906, Kalamazoo County Battery storage |
200 MW | In study |
Kalamazoo, MI | MISO |
Sep 2022 | target 2024 |
Solar project J3286, Sanilac County Solar |
200 MW | In study |
Sanilac, MI | MISO |
Apr 2024 | target 2028 |
Solar project J2485, Livingston County Solar |
200 MW | In study |
Livingston, MI | MISO |
Sep 2022 | target 2025 |
Battery storage project J4053, Grand Traverse County Battery storage |
200 MW | In study |
Grand Traverse, MI | MISO |
Jul 2025 | target 2028 |
Battery storage project J1902, Wayne County Battery storage |
200 MW | In study |
Wayne, MI | MISO |
Aug 2021 | target 2024 |
Solar project J3852, Tuscola County Solar |
200 MW | In study |
Tuscola, MI | MISO |
Dec 2024 | target 2030 |
Solar project J2374, Sanilac County Solar |
200 MW | In study |
Sanilac, MI | MISO |
Sep 2022 | target 2025 |
Battery storage project J4123, Branch County Battery storage |
200 MW | In study |
Branch, MI | MISO |
Sep 2025 | target 2030 |
Solar project J3633, Sanilac County Solar |
200 MW | In study |
Sanilac, MI | MISO |
Apr 2024 | target 2028 |
Solar project J3837, Van Buren County Solar |
200 MW | In study |
Van Buren, MI | MISO |
Dec 2024 | target 2029 |
Solar project J3803, Monroe County Solar |
200 MW | In study |
Monroe, MI | MISO |
Apr 2024 | target 2028 |
Battery storage project J2475, Monroe County Battery storage |
200 MW | In study |
Monroe, MI | MISO |
Sep 2022 | target 2026 |
Onshore wind project J4120, Lenawee County Onshore wind |
200 MW | In study |
Lenawee, MI | MISO |
Sep 2025 | target 2030 |
Battery storage project J3251, Genesee County Battery storage |
200 MW | In study |
Genesee, MI | MISO |
Apr 2024 | target 2028 |
Solar project J2667, Sanilac County Solar |
200 MW | In study |
Sanilac, MI | MISO |
Sep 2022 | target 2025 |
Solar project J3287, Osceola County Solar |
200 MW | In study |
Osceola, MI | MISO |
Apr 2024 | target 2028 |
Solar project J2676, Huron County Solar |
200 MW | In study |
Huron, MI | MISO |
Sep 2022 | target 2025 |
Solar project J2486, Monroe County Solar |
200 MW | In study |
Monroe, MI | MISO |
Sep 2022 | target 2025 |
Onshore wind project J3928, Bay County Onshore wind |
200 MW | In study |
Bay, MI | MISO |
Jan 2025 | target 2030 |
Battery storage project J4019, Calhoun County Battery storage |
200 MW | In study |
Calhoun, MI | MISO |
May 2025 | target 2030 |
Battery storage project J1894, Kalamazoo County Battery storage |
200 MW | In study |
Kalamazoo, MI | MISO |
Oct 2021 | target 2024 |
Battery storage project J1900, Wayne County Battery storage |
200 MW | In study |
Wayne, MI | MISO |
Aug 2021 | target 2024 |