United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in Southeast (non-ISO utilities) (2022 requests) โ€” page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown14217.0 GW
Active in queue17.0 GW142 requests
Agreement signed5,225 MW33 requests
Withdrawn21128.0 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

142 requests ยท page 2 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project IC-1039, Dallas County
Solar
80.0 MWPaused / redesign Dallas, ALSoutheast May 2022target 2026
Solar project 196564, Davidson County
Solar
80.0 MWAgreement signed Davidson, NCSoutheast Jan 2022
Solar + storage project IC-1060, Marengo County
Solar + storage
80.0 MWPaused / redesign Marengo, ALSoutheast Sep 2022target 2027
Solar project 564510, Bladen County
Solar
80.0 MWAgreement signed Bladen, NCSoutheast Jun 2022target 2027
Solar + storage project IC-1053, Hale County
Solar + storage
80.0 MWPaused / redesign Hale, ALSoutheast Aug 2022target 2027
Solar project 569890, Wayne County
Solar
80.0 MWAgreement signed Wayne, NCSoutheast Jun 2022target 2029
Solar + storage project IC-1087, Russell County
Solar + storage
80.0 MWPaused / redesign Russell, ALSoutheast Nov 2022target 2026
Solar project 569632, Scotland County
Solar
80.0 MWUnder construction Scotland, NCSoutheast Jun 2022target 2026
Solar + storage project IC-1052, Lee County
Solar + storage
80.0 MWPaused / redesign Lee, ALSoutheast Aug 2022target 2026
Solar project IC-1036, Montgomery County
Solar
80.0 MWPaused / redesign Montgomery, ALSoutheast May 2022target 2027
Solar + storage project IC-1061, Marengo County
Solar + storage
80.0 MWPaused / redesign Marengo, ALSoutheast Sep 2022target 2027
Solar project IC-1075, Dallas County
Solar
80.0 MWPaused / redesign Dallas, ALSoutheast Oct 2022target 2027
Solar + storage project IC-1086, Perry County
Solar + storage
80.0 MWPaused / redesign Perry, ALSoutheast Nov 2022target 2026
Solar project 568892, Darlington County
Solar ยท Duke Energy Progress, LLC
76.0 MWAgreement signed Darlington, SCSoutheast Jun 2022target 2027
Solar project 565080, Darlington County
Solar
75.0 MWAgreement signed Darlington, SCSoutheast Jun 2022
Solar project 570382, Darlington County
Solar
75.0 MWAgreement signed Darlington, SCSoutheast Jun 2022target 2028
Gas project GI-102, Clinton County
Gas
75.0 MWAgreement signed Clinton, MOSoutheast Jul 2022target 2027
Solar + storage project 425A, Jackson County
Solar + storage ยท Third Party
75.0 MWAgreement signed Jackson, FLSoutheast Feb 2022target 2029
Solar project 566724, Darlington County
Solar
74.9 MWUnder construction Darlington, SCSoutheast Jun 2022target 2026
Solar project 566488, Chesterfield County
Solar
74.9 MWUnder construction Chesterfield, SCSoutheast Jun 2022target 2027
Solar project 307, Suwannee County
Solar ยท CP Ironwood, LLC
74.9 MWPaused / redesign Suwannee, FLSoutheast Apr 2022target 2026
Solar project 319, Hernando County
Solar ยท Duke Energy Florida, LLC
74.9 MWPaused / redesign Hernando, FLSoutheast Dec 2022target 2026
Solar project 322, Sumter County
Solar ยท Duke Energy Florida, LLC
74.9 MWUnder construction Sumter, FLSoutheast Dec 2022target 2026
Solar project 566542, Darlington County
Solar
74.9 MWUnder construction Darlington, SCSoutheast Jun 2022target 2028
Solar project 320, Hernando County
Solar ยท Duke Energy Florida, LLC
74.9 MWPaused / redesign Hernando, FLSoutheast Dec 2022target 2027
Solar project 305, Suwannee County
Solar ยท CP Ironwood, LLC
74.9 MWPaused / redesign Suwannee, FLSoutheast Apr 2022target 2026
Solar project 566518, Darlington County
Solar
74.9 MWUnder construction Darlington, SCSoutheast Jun 2022target 2028
Solar project 566478, Darlington County
Solar
74.9 MWAgreement signed Darlington, SCSoutheast Jun 2022target 2026
Solar project 566202, Anderson County
Solar
74.9 MWAgreement signed Anderson, SCSoutheast Jun 2022target 2031
Solar project 308, Suwannee County
Solar ยท CP Ironwood, LLC
74.9 MWPaused / redesign Suwannee, FLSoutheast Apr 2022target 2026
Solar project 473, Desoto County
Solar ยท FPL
74.5 MWIn study Desoto, FLSoutheast Jul 2022target 2029
Solar project 454, St. Lucie County
Solar ยท FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2030
Solar project 453, St. Lucie County
Solar ยท FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2031
Solar project 437, Manatee County
Solar ยท FPL
74.5 MWIn study Manatee, FLSoutheast Mar 2022target 2026
Solar project 438, Hendry County
Solar ยท FPL
74.5 MWIn study Hendry, FLSoutheast Mar 2022target 2028
Solar project 475, Desoto County
Solar ยท FPL
74.5 MWIn study Desoto, FLSoutheast Jul 2022target 2032
Solar project 451, St. Lucie County
Solar ยท FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2029
Solar project 465, Collier County
Solar ยท FPL
74.5 MWIn study Collier, FLSoutheast Apr 2022target 2029
Solar project 461, Collier County
Solar ยท FPL
74.5 MWIn study Collier, FLSoutheast Apr 2022target 2028
Solar project 434, Desoto County
Solar ยท FPL
74.5 MWIn study Desoto, FLSoutheast Mar 2022target 2027
Solar project 457, St. Lucie County
Solar ยท FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2029
Solar project 430, Desoto County
Solar ยท FPL
74.5 MWIn study Desoto, FLSoutheast Mar 2022target 2026
Solar project 455, St. Lucie County
Solar ยท FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2031
Solar project 471, Desoto County
Solar ยท FPL
74.5 MWIn study Desoto, FLSoutheast Jul 2022target 2029
Solar project 460, Collier County
Solar ยท FPL
74.5 MWIn study Collier, FLSoutheast Apr 2022target 2026
Solar project 462, Collier County
Solar ยท FPL
74.5 MWIn study Collier, FLSoutheast Apr 2022target 2029
Solar project 448, St. Lucie County
Solar ยท FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2029
Solar project 444, St. Lucie County
Solar ยท FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2026
Solar project 459, Collier County
Solar ยท FPL
74.5 MWIn study Collier, FLSoutheast Apr 2022target 2026
Solar project 449, St. Lucie County
Solar ยท FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2029

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)