United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in West (non-ISO utilities) — page 15

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,277949.5 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,277 requests · page 15 of 106
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 2023-G8
Solar
400 MWWithdrawn / abandoned West Sep 2023target 2027
Battery storage project 22-117, Clackamas County
Battery storage
400 MWWithdrawn / abandoned Clackamas, ORWest Dec 2022target 2027
Other project G0903, Linn County
Other
400 MWWithdrawn / abandoned Linn, ORWest Jun 2023target 2030
Solar + storage project C1-22, Iron County
Solar + storage
400 MWWithdrawn / abandoned Iron, UTWest May 2021target 2025
Solar + storage project Q62, Pinal County
Solar + storage
400 MWWithdrawn / abandoned Pinal, AZWest May 2020target 2023
Solar + storage project C4-034, Emery County
Solar + storage
400 MWWithdrawn / abandoned Emery, UTWest May 2024target 2030
Solar + storage project G0741, Klickitat County
Solar + storage
400 MWWithdrawn / abandoned Klickitat, WAWest May 2022target 2024
Solar + storage project Q35, Maricopa County
Solar + storage
400 MWWithdrawn / abandoned Maricopa, AZWest Dec 2022target 2025
Solar + storage project G0913, Deschutes County
Solar + storage
400 MWWithdrawn / abandoned Deschutes, ORWest Jul 2023target 2034
Onshore wind project 1183, Carbon County
Onshore wind
400 MWWithdrawn / abandoned Carbon, WYWest Oct 2019target 2024
Solar + storage project C4-089, Utah County
Solar + storage
400 MWWithdrawn / abandoned Utah, UTWest May 2024target 2027
Solar + storage project Q65, Clark County
Solar + storage
400 MWWithdrawn / abandoned Clark, NVWest Oct 2018target 2021
Solar + storage project Company JJ, Lander County
Solar + storage
400 MWWithdrawn / abandoned Lander, NVWest Sep 2018target 2021
Solar + storage project Q14, Pinal County
Solar + storage
400 MWWithdrawn / abandoned Pinal, AZWest Jun 2020target 2023
Solar + storage project 663, Ada County
Solar + storage
400 MWWithdrawn / abandoned Ada, IDWest Jul 2022
Onshore wind project 343, Millard County
Onshore wind
398 MWWithdrawn / abandoned Millard, UTWest Jun 2010target 2013
Solar project Q39, Kern County
Solar
396 MWWithdrawn / abandoned Kern, CAWest Nov 2012target 2015
Onshore wind project 31, Stillwater County
Onshore wind
396 MWWithdrawn / abandoned Stillwater, MTWest May 2004target 2011
Battery storage project G0607, Klamath County
Battery storage
394 MWWithdrawn / abandoned Klamath, ORWest Dec 2018target 2025
Onshore wind project Q90, Navajo County
Onshore wind
390 MWWithdrawn / abandoned Navajo, AZWest Dec 2009target 2016
Onshore wind project 1156, Carbon County
Onshore wind
380 MWWithdrawn / abandoned Carbon, WYWest Aug 2019target 2023
Gas project 264, Weber County
Gas
380 MWWithdrawn / abandoned Weber, UTWest Mar 2009target 2012
Gas project 246, Salt Lake County
Gas
380 MWWithdrawn / abandoned Salt Lake, UTWest Nov 2008target 2012
Gas project 308, Salt Lake County
Gas · Parowan Solar Energy, LLC
380 MWWithdrawn / abandoned Salt Lake, UTWest Dec 2009target 2014
Gas project 244, Weber County
Gas
380 MWWithdrawn / abandoned Weber, UTWest Nov 2008target 2012
Gas project 245, Salt Lake County
Gas
380 MWWithdrawn / abandoned Salt Lake, UTWest Nov 2008target 2012
Other project G1005, Klickitat County
Other
380 MWWithdrawn / abandoned Klickitat, WAWest Nov 2023target 2028
Gas project 419, Cowlitz County
Gas
375 MWWithdrawn / abandoned Cowlitz, WAWest Mar 2012target 2015
Solar project 772, Iron County
Solar
375 MWWithdrawn / abandoned Iron, UTWest Jul 2016target 2018
Solar + storage project IA-PNM-2022-09, Mckinley County
Solar + storage
375 MWWithdrawn / abandoned Mckinley, NMWest Apr 2022target 2025
Solar + storage project TCS-15, Adams County
Solar + storage
375 MWWithdrawn / abandoned Adams, WAWest Jan 2021target 2024
Onshore wind project 535, Jerome County
Onshore wind
375 MWWithdrawn / abandoned Jerome, IDWest Jun 2018
Solar + storage project GI-2020-13, Pueblo County
Solar + storage
374 MWWithdrawn / abandoned Pueblo, COWest Sep 2020target 2024
Solar + storage project Q2517, Pinal County
Solar + storage
373 MWWithdrawn / abandoned Pinal, AZWest Feb 2025target 2028
Solar + storage project Company 235, Nye County
Solar + storage
370 MWWithdrawn / abandoned Nye, NVWest Jan 2023target 2026
Gas project 23, Skagit County
Gas
367 MWWithdrawn / abandoned Skagit, WAWest Apr 2010target 2017
Onshore wind project 300, Rich County
Onshore wind
362 MWWithdrawn / abandoned Rich, UTWest Oct 2009target 2013
Onshore wind project GI-2021-25, Morgan County
Onshore wind
362 MWWithdrawn / abandoned Morgan, COWest Oct 2021target 2024
Onshore wind project 132, Albany County
Onshore wind
361 MWWithdrawn / abandoned Albany, WYWest May 2007target 2012
Solar + storage project Company KQ, Pershing County
Solar + storage
360 MWWithdrawn / abandoned Pershing, NVWest Sep 2020target 2026
Solar + storage project 9, Sacramento County
Solar + storage
360 MWWithdrawn / abandoned Sacramento, CAWest Mar 2021target 2023
Solar project Q335, Yavapai County
Solar
360 MWWithdrawn / abandoned Yavapai, AZWest Mar 2020target 2023
Solar + storage project Q545, Yavapai County
Solar + storage
360 MWWithdrawn / abandoned Yavapai, AZWest Sep 2023target 2027
Gas project Company HA, Washoe County
Gas
360 MWWithdrawn / abandoned Washoe, NVWest Nov 2015target 2018
Gas project Q03, Pinal County
Gas
352 MWWithdrawn / abandoned Pinal, AZWest Sep 2008target 2012
Solar project Q54, Pinal County
Solar
352 MWWithdrawn / abandoned Pinal, AZWest Oct 2008target 2012
Onshore wind project GI-2018-14, Banner County
Onshore wind
350 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-2018-13, Banner County
Onshore wind
350 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Solar + storage project Company PP, Eureka County
Solar + storage
350 MWWithdrawn / abandoned Eureka, NVWest Mar 2023target 2025
Solar project Company 96, Clark County
Solar
350 MWWithdrawn / abandoned Clark, NVWest Sep 2010target 2012
Page 15 of 106

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)