United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2010 requests) โ€” page 11

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,016100.7 GW
Active in queue2,652 MW13 requests
Agreement signed1,364 MW9 requests
Withdrawn1,016100.7 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,016 requests ยท page 11 of 21
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project 355, Elmore County
Onshore wind
20.0 MWWithdrawn / abandoned Elmore, IDWest Sep 2010
Bio Verde PV - Hoogendm
Solar
20.0 MWWithdrawn / abandoned Merced, CACAISO Feb 2010target 2012
Solar project Q121, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Apr 2010target 2012
Sirius Solar
Solar
20.0 MWWithdrawn / abandoned Kern, CACAISO Aug 2010target 2017
Solar project Q128, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Apr 2010target 2011
Solar project W1-118, Cumberland County
Solar
20.0 MWWithdrawn / abandoned Cumberland, NJPJM Apr 2010target 2011
Sun Stream
Solar
20.0 MWWithdrawn / abandoned Kern, CACAISO Mar 2010target 2012
Onshore wind project W3-039, Hudson County
Onshore wind
20.0 MWWithdrawn / abandoned Hudson, NJPJM Aug 2010target 2012
Solar project W4-035, Clinton County
Solar
20.0 MWWithdrawn / abandoned Clinton, OHPJM Dec 2010target 2012
Solar project W4-028, Salem County
Solar
20.0 MWWithdrawn / abandoned Salem, NJPJM Dec 2010target 2011
Sunshine Four
Solar
20.0 MWWithdrawn / abandoned Los Angeles, CACAISO Jan 2010target 2011
Solar project W2-101, Salem County
Solar
20.0 MWWithdrawn / abandoned Salem, NJPJM Jul 2010target 2017
Solar project W1-117, Cumberland County
Solar
20.0 MWWithdrawn / abandoned Cumberland, NJPJM Apr 2010target 2011
Solar project W1-087, Cumberland County
Solar
20.0 MWWithdrawn / abandoned Cumberland, NJPJM Apr 2010target 2011
Solar project GEN-2010-058, Chaves County
Solar
20.0 MWWithdrawn / abandoned Chaves, NMSPP Nov 2010target 2011
Other project 335, Ada County
Other
20.0 MWWithdrawn / abandoned Ada, IDWest Jun 2010
Solar project W1-075, Adams County
Solar
20.0 MWWithdrawn / abandoned Adams, PAPJM Apr 2010target 2012
Solar project W3-163, Salem County
Solar
20.0 MWWithdrawn / abandoned Salem, NJPJM Oct 2010target 2011
Solar project Q156, Navajo County
Solar
20.0 MWWithdrawn / abandoned Navajo, AZWest Jun 2010target 2012
Thunderhill Solar Power
Solar
20.0 MWWithdrawn / abandoned Glenn, CACAISO Jul 2010target 2011
Onshore wind project 353, Blaine County
Onshore wind
20.0 MWWithdrawn / abandoned Blaine, IDWest Aug 2010
Solar project Q148, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Jun 2010target 2012
Solar project W1-042, Franklin County
Solar
20.0 MWWithdrawn / abandoned Franklin, PAPJM Mar 2010target 2011
Solar project Q147, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Jun 2010target 2012
Solar project Q116, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Mar 2010target 2012
Stacy Haines Road
Solar
20.0 MWWithdrawn / abandoned Burlington, NJPJM Jul 2010target 2016
Bio Verde PV - Kettleman 3
Solar
20.0 MWWithdrawn / abandoned Kings, CACAISO Feb 2010target 2012
Solar project Q163, Yuma County
Solar
20.0 MWWithdrawn / abandoned Yuma, AZWest Aug 2010target 2012
Onshore wind project 354, Elmore County
Onshore wind
20.0 MWWithdrawn / abandoned Elmore, IDWest Sep 2010
Solar project Q16, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Oct 2010target 2012
Solar project W1-093, Cape May County
Solar
20.0 MWWithdrawn / abandoned Cape May, NJPJM Apr 2010target 2011
Solar project W1-128, Warren County
Solar
20.0 MWWithdrawn / abandoned Warren, NJPJM Apr 2010target 2011
Solar project 358, Owyhee County
Solar
20.0 MWWithdrawn / abandoned Owyhee, IDWest Oct 2010
Solar project Company 95, Clark County
Solar
20.0 MWWithdrawn / abandoned Clark, NVWest Apr 2010target 2011
Cove Creek Solar Project
Solar
20.0 MWWithdrawn / abandoned Fulton, PAPJM Dec 2010target 2014
Solar project W2-098, Adams County
Solar
20.0 MWWithdrawn / abandoned Adams, PAPJM Jul 2010target 2013
Solar project Q140, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Jun 2010target 2012
Solar project Q99, La Paz County
Solar
20.0 MWWithdrawn / abandoned La Paz, AZWest Feb 2010target 2011
Solar project W3-037, Wicomico County
Solar
20.0 MWWithdrawn / abandoned Wicomico, MDPJM Aug 2010target 2012
Solar project W1-070, Wicomico County
Solar
20.0 MWWithdrawn / abandoned Wicomico, MDPJM Apr 2010target 2011
Bio Verde PV - San Joaquin
Solar
20.0 MWWithdrawn / abandoned San Joaquin, CACAISO Feb 2010target 2012
Solar project Q135, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Apr 2010target 2011
Solar project Q12, Pinal County
Solar
20.0 MWWithdrawn / abandoned Pinal, AZWest Jul 2010target 2012
Solar project Q19, Pinal County
Solar
20.0 MWWithdrawn / abandoned Pinal, AZWest Nov 2010target 2012
Solar project Q167, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Oct 2010target 2013
Solar project Q174, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Dec 2010target 2013
Solar project W2-032, Cumberland County
Solar
20.0 MWWithdrawn / abandoned Cumberland, NJPJM Jun 2010target 2011
Solar project W1-037
Solar
20.0 MWWithdrawn / abandoned VAPJM Feb 2010target 2011
Solar project Q103, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Feb 2010target 2012
Rio Bravo Solar I
Solar
20.0 MWWithdrawn / abandoned Kern, CACAISO Nov 2010target 2013

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)