🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

SOLAR · CAISO

Bio Verde PV - Hoogendm

Bio Verde PV - Hoogendm is a 20.0 MW solar request withdrawn in the CAISO interconnection queue, in Merced County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2010 (completed)
  2. Withdrawn / abandonedNov 2010 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
594
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Merced Substation 70 kV
Location
Merced County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
1 February 2010
Proposed online date
December 2012
Withdrawn
November 2010

Location

Marker shows the centre of Merced County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Merced County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem