🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in West (non-ISO utilities) — page 11

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,496455.6 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,496 requests · page 11 of 30
ProjectCapacityStatusLocationRegionQueuedOnline
Other project G0693, Crook County
Other
300 MWIn study Crook, ORWest Sep 2021target 2025
Solar + storage project 5RSC-2024-06, Pueblo County
Solar + storage
300 MWIn study Pueblo, COWest Jan 2024target 2028
Solar + storage project Company LL, Pershing County
Solar + storage
300 MWPaused / redesign Pershing, NVWest Mar 2021target 2029
Other project 78, Apache County
Other
300 MWIn study Apache, AZWest Feb 2020target 2023
Solar + storage project C2-72, Tooele County
Solar + storage
300 MWIn study Tooele, UTWest May 2022target 2025
Battery storage project Q467, Maricopa County
Battery storage
300 MWIn study Maricopa, AZWest Mar 2022target 2026
Solar + storage project 2022-G9, Pinal County
Solar + storage
300 MWIn study Pinal, AZWest Jul 2022target 2025
Solar + storage project G0865, Sherman County
Solar + storage
300 MWIn study Sherman, ORWest Jun 2023target 2027
Onshore wind project NC5-009, Mohave County
Onshore wind
300 MWIn study Mohave, AZWest Apr 2022target 2027
Solar project 25-00381, Lassen County
Solar
300 MWIn study Lassen, CAWest Jul 2025target 2029
Solar + storage project 124, Pinal County
Solar + storage
300 MWIn study Pinal, AZWest Jun 2022target 2025
Onshore wind project G0918, Lane County
Onshore wind
300 MWIn study Lane, ORWest Aug 2023target 2029
Solar + storage project GI-2025-02, Cheyenne County
Solar + storage
300 MWIn study Cheyenne, COWest Apr 2025target 2030
Other project G0924, Walla Walla County
Other
300 MWIn study Walla Walla, WAWest Sep 2023target 2027
Atrisco Solar II
Solar + storage
300 MWPaused / redesign Bernalillo, NMWest Oct 2020target 2023
Battery storage project Q314, Maricopa County
Battery storage
300 MWIn study Maricopa, AZWest Sep 2019target 2022
Onshore wind project 406, Rosebud County
Onshore wind
300 MWIn study Rosebud, MTWest Feb 2021target 2024
Other project Q597, Yuma County
Other
300 MWIn study Yuma, AZWest May 2025target 2029
Onshore wind project T2-025, Bingham County
Onshore wind
300 MWIn study Bingham, IDWest Sep 2025target 2030
Other project GI-CS-2025-29, Yuma County
Other
300 MWIn study Yuma, COWest Oct 2025target 2031
Solar + storage project 2023-G17, Mohave County
Solar + storage
300 MWIn study Mohave, AZWest Dec 2023target 2027
Other project Q586, Maricopa County
Other
300 MWIn study Maricopa, AZWest May 2025target 2030
Onshore wind project Company LF, Lassen County
Onshore wind
300 MWPaused / redesign Lassen, CAWest Mar 2021target 2023
Solar + storage project GI-DISIS-2021-11, Las Animas County
Solar + storage
300 MWPaused / redesign Las Animas, COWest May 2021target 2026
Solar + storage project Q443, Yuma County
Solar + storage
300 MWIn study Yuma, AZWest Mar 2022target 2027
Other project G0925, Walla Walla County
Other
300 MWIn study Walla Walla, WAWest Sep 2023target 2027
Onshore wind project Q86, Millard County
Onshore wind · Intermountain Power Agency
300 MWIn study Millard, UTWest Nov 2021target 2025
Gas project PIS040, Utah County
Gas
300 MWIn study Utah, UTWest Jun 2023target 2026
Onshore wind project G0973, Mason County
Onshore wind
300 MWIn study Mason, WAWest Oct 2023target 2029
Solar + storage project 9, Grant County
Solar + storage
300 MWIn study Grant, WAWest Sep 2023
Solar + storage project GI-2025-01, Morgan County
Solar + storage
300 MWIn study Morgan, COWest Apr 2025target 2030
Other project Q570, Yuma County
Other
300 MWIn study Yuma, AZWest May 2024target 2028
Solar + storage project GI-CS-2025-03, Kit Carson County
Solar + storage
300 MWIn study Kit Carson, COWest Sep 2025target 2028
Solar + storage project Company NS, Eureka County
Solar + storage
300 MWPaused / redesign Eureka, NVWest Sep 2022target 2029
Other project 608, Sweetwater County
Other · NextEra Energy Resources Interconnection Holdings, LLC
300 MWPaused / redesign Sweetwater, WYWest Jun 2021target 2025
Dworshak Fourth Unit
Hydro
300 MWIn study Clearwater, IDWest Aug 2013target 2019
Solar + storage project G0639, Douglas County
Solar + storage
300 MWIn study Douglas, WAWest Feb 2020target 2023
Onshore wind project Company NA, White Pine County
Onshore wind
300 MWPaused / redesign White Pine, NVWest Mar 2022target 2030
Solar + storage project T2-056, Juab County
Solar + storage
300 MWIn study Juab, UTWest Sep 2025target 2029
Solar + storage project TCS-09, Utah County
Solar + storage · Longroad Development Company, LLC
300 MWPaused / redesign Utah, UTWest Nov 2017target 2023
Onshore wind project 118, Apache County
Onshore wind
300 MWIn study Apache, AZWest Apr 2022target 2025
Solar + storage project 2019-G1, Butte County
Solar + storage
300 MWIn study Butte, CAWest Aug 2019target 2027
Onshore wind project CS25-11, Garfield County
Onshore wind
300 MWIn study Garfield, WAWest Apr 2025target 2029
Solar + storage project Q2402, Maricopa County
Solar + storage
300 MWIn study Maricopa, AZWest Feb 2024target 2027
Solar project 405, Rosebud County
Solar
300 MWPaused / redesign Rosebud, MTWest Feb 2021target 2024
Solar + storage project Company MJ, Lyon County
Solar + storage
300 MWPaused / redesign Lyon, NVWest Sep 2021target 2029
Other project G0923, Walla Walla County
Other
300 MWIn study Walla Walla, WAWest Sep 2023target 2027
Solar + storage project T2-028, Iron County
Solar + storage
300 MWIn study Iron, UTWest Sep 2025target 2029
Solar + storage project 656, Jerome County
Solar + storage · Red Bridge Energy, LLC
300 MWPaused / redesign Jerome, IDWest May 2022target 2027
Solar + storage project G1047, Grant County
Solar + storage
300 MWIn study Grant, WAWest Nov 2023target 2026
Page 11 of 30

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)