Requests shown47497.1 GW
Active in queue452.0 GW1,836 requests
Agreement signed4,701 MW27 requests
Withdrawn47497.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

474 requests Β· page 10 of 10
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AH1-274, Gloucester County
Solar Β· Vineland Newfield Solar Farm, LLC
16.7 MWWithdrawn / abandoned Gloucester, NJPJM Mar 2025target 2022
Delek Big Spring Storage
Battery storage Β· TotalEnergies Distributed Generation USA, LLC
15.3 MWWithdrawn / abandoned Howard, TXERCOT Feb 2025target 2027
Solar project AG2-112, Halifax County
Solar Β· Kangaroo Solar, LLC
15.2 MWWithdrawn / abandoned Halifax, VAPJM Feb 2025target 2023
Solar project AG2-654, Armstrong County
Solar Β· IMG Solar LLC
14.7 MWWithdrawn / abandoned Armstrong, PAPJM Jan 2025target 2022
Solar project AG2-111, Campbell County
Solar Β· Koala Solar, LLC
14.5 MWWithdrawn / abandoned Campbell, VAPJM Feb 2025target 2023
Hydro project AG2-505, Garrett County
Hydro Β· Fairlawn Hydroelectric Company, LLC
14.0 MWWithdrawn / abandoned Garrett, MDPJM Mar 2025target 2023
Nuclear project 25-IC-1305, Burke County
Nuclear
14.0 MWWithdrawn / abandoned Burke, GASoutheast Mar 2025
Solar project AG2-090, Somerset County
Solar Β· Neptune Solar LLC
14.0 MWWithdrawn / abandoned Somerset, PAPJM Mar 2025target 2023
Solar project AG2-438, Erie County
Solar Β· Clemens Solar LLC
10.0 MWWithdrawn / abandoned Erie, PAPJM Jan 2025target 2023
Tennessee Gas-East Towanda 115 kV
Solar Β· Agnes Solar, LLC
10.0 MWWithdrawn / abandoned Bradford, PANYISO Sep 2025
Churchill Storage Solutions LLC
Battery storage Β· Churchill Storage Solutions LLC
10.0 MWWithdrawn / abandoned City Of Hopewell, VAPJM Feb 2025target 2023
Solar project AG2-327, Bradford County
Solar Β· Agnes Solar LLC
10.0 MWWithdrawn / abandoned Bradford, PAPJM Feb 2025target 2023
Wieland Substation BESS Unit 1
Battery storage Β· Telios Quinlan Energy One, LLC
9.9 MWWithdrawn / abandoned ERCOT Mar 2025target 2026
Solar project AG2-439, Wyoming County
Solar Β· Field Brook Solar LLC
9.8 MWWithdrawn / abandoned Wyoming, PAPJM Feb 2025target 2023
Oxbow 34.5 kV
Solar Β· Field Brook Solar LLC
9.8 MWWithdrawn / abandoned Wyoming, PANYISO Sep 2025
Solar project AG2-091, Somerset County
Solar Β· Neptune Solar LLC
6.0 MWWithdrawn / abandoned Somerset, PAPJM Mar 2025target 2023
Solar project CS25-18, Spokane County
Solar
5.0 MWWithdrawn / abandoned Spokane, WAWest Apr 2025target 2026
BESS
Battery storage
5.0 MWWithdrawn / abandoned Essex, MAISO-NE Jan 2025target 2027
Solar project T2-068, Jackson County
Solar
3.0 MWWithdrawn / abandoned Jackson, ORWest Sep 2025target 2025
Solar project T2-067, Linn County
Solar
3.0 MWWithdrawn / abandoned Linn, ORWest Sep 2025target 2025
Solar project T2-066, Jefferson County
Solar
3.0 MWWithdrawn / abandoned Jefferson, ORWest Sep 2025target 2025
Solar project T2-065, Jefferson County
Solar
3.0 MWWithdrawn / abandoned Jefferson, ORWest Sep 2025target 2025
Solar project T2-064, Umatilla County
Solar
3.0 MWWithdrawn / abandoned Umatilla, ORWest Sep 2025target 2025
Solar project 977129, Abbeville County
Solar
2.5 MWWithdrawn / abandoned Abbeville, SCSoutheast Jun 2025
Page 10 of 10

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)