Worksop
Worksop is a 2 MW onshore wind farm in East Midlands England, operated by Ecotricity. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- Onshore
- East Midlands
- England
Key facts
- Installed capacity
- 2 MW
- Status
- Operational
- Technology
- Wind Β· Onshore
- Operator
- Ecotricity
- Region
- East Midlands
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- S80 2PU
- Coordinates
- 53.2998, -1.0757
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Worksop compares
At a typical UK load factor for this technology (about 26% of the maximum possible output), a 2 MW station would generate roughly 4.6 GWh of electricity in a year, similar to the annual use of about 1,690 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.
All UK wind farms Wind farms in East Midlands All run by EcotricityNearby generating sites
- Morton Solar Β· 28.1 MW solar farm5.5 km
- Little Morton Β· 14.3 MW solar farm5.5 km
- Welbeck Β· 16 MW solar farm5.9 km
- Moat Farm Β· 4.62 MW solar farm7.6 km
- Thoresby Β· 19.8 MW solar farm8.4 km
- Hunciecroft Β· 7.62 MW solar farm8.5 km
- Cottam Development Centre Β· 445 MW CCGT gas power station8.6 km
- Welbeck Β· 11.3 MW solar farm9.4 km
Also operated by Ecotricity
Ecotricity operates 25 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Worksop - B&Q
- Developer / operator
- Ecotricity
- Planning authority
- Bassetlaw
- Planning reference
- 1/2/07/528
- Application submitted
- 7 September 2007
- Permission granted
- 1 November 2007
- Construction started
- 1 December 2008
- Began operating
- 21 January 2009
- Capacity in planning record
- 2 MW
- Address
- Manton Wood, Worksop, Nottinghamshire, Nottinghamshire
- REPD reference
- 3510
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.