Hunciecroft
Hunciecroft is a 7.62 MW solar farm in East Midlands England, operated by Greencoat Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- East Midlands
- England
Key facts
- Installed capacity
- 7.62 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Greencoat Capital
- Region
- East Midlands
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- S80 3ND
- Coordinates
- 53.2594, -1.1843
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Hunciecroft compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 7.62 MW station would generate roughly 6.7 GWh of electricity in a year, similar to the annual use of about 2,470 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in East Midlands All run by Greencoat CapitalNearby generating sites
- Welbeck Β· 11.3 MW solar farm5.0 km
- Bolsovermoor Quarry Β· 5 MW solar farm5.3 km
- 30Acres Β· 3.77 MW solar farm6.1 km
- Welbeck Β· 16 MW solar farm6.2 km
- Barlborough Β· 0.85 MW onshore wind farm6.3 km
- Thoresby Β· 19.8 MW solar farm6.9 km
- Loscar Β· 4.5 MW onshore wind farm7.0 km
- Oxcroft Β· 4.19 MW solar farm8.0 km
Also operated by Greencoat Capital
Greencoat Capital operates 195 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Hunciecroft Farm
- Developer / operator
- Solar century / Magnetar Solar
- Planning authority
- Bassetlaw
- Planning reference
- 14/01015/FUL
- Application submitted
- 15 August 2014
- Permission granted
- 20 November 2014
- Construction started
- 1 January 2015
- Began operating
- 6 March 2015
- Capacity in planning record
- 8 MW
- Address
- Land North West Of Hunciecroft Farm Holbeck Lane Holbeck Nottinghamshire, Nottinghamshire
- REPD reference
- 2192
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.