Galsworthy is a 9.2 MW onshore wind farm in South West England, operated by Ecotricity. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- Onshore
- South West
- England
Key facts
- Installed capacity
- 9.2 MW
- Status
- Operational
- Technology
- Wind Β· Onshore
- Operator
- Ecotricity
- Region
- South West
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- EX39 5NP
- Coordinates
- 50.9205, -4.2776
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Galsworthy compares
At a typical UK load factor for this technology (about 26% of the maximum possible output), a 9.2 MW station would generate roughly 21 GWh of electricity in a year, similar to the annual use of about 7,760 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.
All UK wind farms Wind farms in South West All run by EcotricityNearby generating sites
- Bulkworthy Solar Β· 6.24 MW solar farm1.2 km
- Southcombe Farm Β· 1.21 MW solar farm5.8 km
- Walland Farm Β· 5 MW solar farm7.8 km
- Dunsland Cross Β· 6.15 MW onshore wind farm8.9 km
- Week Farm 2 Β· 3.73 MW solar farm11.6 km
- East Langford Solar Β· 5 MW solar farm11.9 km
- East Youlstone Β· 4 MW onshore wind farm12.4 km
- Knockworthy Farm Solar Park Β· 4.65 MW solar farm13.0 km
Also operated by Ecotricity
Ecotricity operates 25 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Galsworthy Wind Park
- Developer / operator
- Ecotricity
- Planning authority
- Torridge
- Planning reference
- 1/0375/2008/FUL
- Application submitted
- 4 April 2008
- Permission granted
- 11 September 2008
- Construction started
- 1 May 2011
- Began operating
- 28 November 2014
- Capacity in planning record
- 9.2 MW
- Address
- Land At Galsworthy , Buckland Brewer And Bulkworthy, Devon
- REPD reference
- 4624
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.