WIND Β· OPERATIONAL

Potato Pot

Potato Pot is a 7.05 MW onshore wind farm in North West England, operated by Capital Dynamics UK. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • North West
  • England
Project stageOperating
  1. PlanningAug 2012 (completed)
  2. ConsentedOct 2013 (completed)
  3. ConstructionSep 2015 (completed)
  4. OperatingSep 2016 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
7.05 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
Capital Dynamics UK
Region
North West
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
CA14 4ST
Coordinates
54.6027, -3.5031

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Potato Pot compares

378th of 488largest wind farms in the UK register
19th of 32in North West
0.02%of listed UK wind farms capacity
β‰ˆ 16 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 7.05 MW station would generate roughly 16 GWh of electricity in a year, similar to the annual use of about 5,950 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in North West All run by Capital Dynamics UK

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Potato Pot Wind Farm
Developer / operator
Capital Dynamics
Planning authority
Cumberland
Planning reference
2/2012/0594
Application submitted
7 August 2012
Permission granted
23 October 2013
Construction started
15 September 2015
Began operating
15 September 2016
Capacity in planning record
6 MW
Address
Land at Potato Pot Branthwaite Workington Cumbria, Cumbria
REPD reference
4233

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.