WIND Β· OPERATIONAL

Mynydd Gorddu

Mynydd Gorddu is a 10.2 MW onshore wind farm in Wales, operated by Venitent Energy Services. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • Wales
Project stageOperating
  1. PlanningJan 1991 (completed)
  2. ConsentedSep 1991 (completed)
  3. Construction (completed)
  4. OperatingApr 1998 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
10.2 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
Venitent Energy Services
Region
Wales
Country
Wales
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
SY24 5DP
Coordinates
52.4663, -3.9710

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Mynydd Gorddu compares

324th of 488largest wind farms in the UK register
25th of 43in Wales
0.03%of listed UK wind farms capacity
β‰ˆ 23 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 10.2 MW station would generate roughly 23 GWh of electricity in a year, similar to the annual use of about 8,600 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in Wales All run by Venitent Energy Services

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Mynydd Gorddu Wind Farm
Developer / operator
Cynllun Trydan Gwynt
Planning authority
Ceredigion
Application submitted
4 January 1991
Permission granted
12 September 1991
Began operating
18 April 1998
Capacity in planning record
10.2 MW
Address
Mynydd Gorddu Elerch Tal-y-Bont Dyfed, Dyfed
REPD reference
2559

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.