πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
WIND Β· OPERATIONAL

Knabs Ridge

Knabs Ridge is a 16 MW onshore wind farm in Yorkshire and the Humber, England, operated by RWE Npower. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • Yorkshire and the Humber
  • England

Key facts

Installed capacity
16 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
RWE Npower
Region
Yorkshire and the Humber
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Coordinates
53.9990, -1.6496

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Knabs Ridge compares

257th of 488largest wind farms in the UK register
16th of 31in Yorkshire and the Humber
0.05%of listed UK wind farms capacity
β‰ˆ 36 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 16 MW station would generate roughly 36 GWh of electricity in a year, similar to the annual use of about 13,500 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in Yorkshire and the Humber All run by RWE Npower

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Knabs Ridge Windfarm
Developer / operator
RWE npower
Planning authority
North Yorkshire
Planning reference
6.99.144.B.EIAMAG
Application submitted
23 April 2004
Permission granted
4 November 2004
Construction started
1 March 2007
Began operating
22 April 2008
Capacity in planning record
16 MW
Address
Land between Skipton Road and Penny Pot Lane, Selliscliffe, Harrogate, North Yorkshire
REPD reference
3147

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.