Greater Gabbard is a 504 MW offshore wind farm in East of England, England, operated by SSE Group. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Offshore
  • East of England
  • England
Project stageOperating
  1. PlanningOct 2005 (completed)
  2. ConsentedFeb 2007 (completed)
  3. ConstructionJul 2009 (completed)
  4. OperatingSep 2012 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
504 MW
Status
Operational
Technology
Wind Β· Offshore
Operator
SSE Group
Region
East of England
Country
England
Grid connection (DUKES)
HV
Combined heat & power
No
Coordinates
51.9176, 1.9284

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Greater Gabbard compares

13th of 488largest wind farms in the UK register
3rd of 48in East of England
1.7%of listed UK wind farms capacity
β‰ˆ 1,678 GWhillustrative output a year

At a typical UK load factor for this technology (about 38% of the maximum possible output), a 504 MW station would generate roughly 1,678 GWh of electricity in a year, similar to the annual use of about 621,380 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in East of England All run by SSE Group

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Greater Gabbard Wind Farm
Developer / operator
Airtricity / Fluor Ltd
Planning authority
DECC (S36)
Application submitted
17 October 2005
Permission granted
20 February 2007
Construction started
1 July 2009
Began operating
7 September 2012
Capacity in planning record
504 MW
Address
Near the Suffolk Coast (26km out to sea), Offshore
REPD reference
2510

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.