Westwood
Westwood is a 9.18 MW solar farm in South East England, operated by Lightsource BP. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- South East
- England
Key facts
- Installed capacity
- 9.18 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Lightsource BP
- Region
- South East
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- CT12 5AS
- Coordinates
- 51.3519, 1.3745
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Westwood compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 9.18 MW station would generate roughly 8.0 GWh of electricity in a year, similar to the annual use of about 2,980 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in South East All run by Lightsource BPNearby generating sites
- Manston Β· 9.83 MW solar farm0.5 km
- Manston Thorne Β· 6.2 MW solar farm2.5 km
- Knowlton Β· 11.5 MW solar farm15.1 km
- Woodlands Farm Β· 13.2 MW solar farm17.8 km
- Owls Hatch Β· 51.9 MW solar farm19.2 km
- Thanet Β· 300 MW offshore wind farm20.0 km
- Kentish Flats Extension Β· 49.5 MW offshore wind farm21.5 km
- Guston Β· 5 MW solar farm22.8 km
Also operated by Lightsource BP
Lightsource BP operates 129 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Manston Solar Farm extension (Westwood)
- Developer / operator
- Sunsave 16 Ltd/ Vogt Solar
- Planning authority
- Thanet
- Planning reference
- F/TH/13/0315
- Application submitted
- 10 May 2013
- Permission granted
- 24 July 2013
- Began operating
- 28 March 2014
- Capacity in planning record
- 9.2 MW
- Address
- LAND TO SOUTH SIDE OF PRESTON ROAD RAMSGATE, Kent
- REPD reference
- 1359
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.