SOLAR Β· OPERATIONAL

Vine Farm

Vine Farm is a 45.9 MW solar farm in East of England, England, operated by Greencoat Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • East of England
  • England

Key facts

Installed capacity
45.9 MW
Status
Operational
Technology
Solar Β· PV
Operator
Greencoat Capital
Region
East of England
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
SG8 0HJ
Coordinates
52.1111, -0.0691

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Vine Farm compares

17th of 662largest solar farms in the UK register
4th of 76in East of England
0.81%of listed UK solar farms capacity
β‰ˆ 40 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 45.9 MW station would generate roughly 40 GWh of electricity in a year, similar to the annual use of about 14,900 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in East of England All run by Greencoat Capital

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Vine Farm Solar Park
Developer / operator
Allianz
Planning authority
South Cambridgeshire
Planning reference
S/1067/14/FL
Application submitted
9 May 2014
Construction started
1 August 2015
Began operating
15 March 2016
Capacity in planning record
45 MW
Address
Vine House, Vine Farm, High Street, Shingay Cum Wendy, Royston, Cambridgeshire, SG8 0HJ
REPD reference
2329

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.