The Breck
The Breck is a 5 MW solar farm in East Midlands England, operated by Octopus Investments. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- East Midlands
- England
Key facts
- Installed capacity
- 5 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Octopus Investments
- Region
- East Midlands
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- S43 2NP
- Coordinates
- 53.2803, -1.3667
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How The Breck compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 5 MW station would generate roughly 4.4 GWh of electricity in a year, similar to the annual use of about 1,620 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in East Midlands All run by Octopus InvestmentsNearby generating sites
- Arkwright CIC Β· 2.48 MW solar farm4.3 km
- Arkwright SPV Β· 5 MW solar farm4.3 km
- Oxcroft Β· 4.19 MW solar farm4.5 km
- Lodge Farm Β· 4.88 MW solar farm5.2 km
- Barlborough Β· 0.85 MW onshore wind farm6.7 km
- Bolsovermoor Quarry Β· 5 MW solar farm9.0 km
- Loscar Β· 4.5 MW onshore wind farm9.5 km
- Penny Hill Wind Farm Β· 20.4 MW onshore wind farm12.3 km
Also operated by Octopus Investments
Octopus Investments operates 134 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Developer / operator
- Lightsource Renewable Energy
- Planning authority
- Chesterfield
- Planning reference
- CHE/15/00460/FUL
- Application submitted
- 31 July 2015
- Permission granted
- 27 October 2015
- Construction started
- 1 February 2016
- Began operating
- 17 March 2016
- Capacity in planning record
- 5 MW
- Address
- The Breck, Breck Lane, Barrow Hill, Chesterfield, Derbyshire, S43 2NP
- REPD reference
- 5520
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.