SOLAR Β· OPERATIONAL

Saron

Saron is a 6.33 MW solar farm in Wales, operated by Greencoat Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • Wales
Project stageOperating
  1. PlanningApr 2013 (completed)
  2. ConsentedSep 2013 (completed)
  3. ConstructionNov 2014 (completed)
  4. OperatingFeb 2015 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
6.33 MW
Status
Operational
Technology
Solar Β· PV
Operator
Greencoat Capital
Region
Wales
Country
Wales
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
SA18 3TW
Coordinates
51.7953, -4.0184

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Saron compares

210th of 662largest solar farms in the UK register
22nd of 75in Wales
0.11%of listed UK solar farms capacity
β‰ˆ 5.5 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 6.33 MW station would generate roughly 5.5 GWh of electricity in a year, similar to the annual use of about 2,050 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in Wales All run by Greencoat Capital

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Saron Road solar park
Developer / operator
Anesco
Planning authority
Carmarthenshire
Planning reference
E/28054
Application submitted
12 April 2013
Permission granted
19 September 2013
Construction started
24 November 2014
Began operating
15 February 2015
Capacity in planning record
6.7 MW
Address
E/O Saron Road, N/O Dyffryn Road, Saron, Ammanford, Dyfed, Dyfed, SA18 3TW
REPD reference
2355

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.