πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
SOLAR Β· OPERATIONAL

New Row Farm

New Row Farm is a 4.45 MW solar farm in South West England, operated by Octopus Investments. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • South West
  • England
Project stageOperating
  1. PlanningAug 2013 (completed)
  2. ConsentedNov 2013 (completed)
  3. Construction (completed)
  4. OperatingMar 2014 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
4.45 MW
Status
Operational
Technology
Solar Β· PV
Operator
Octopus Investments
Region
South West
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
BA4 4JT
Coordinates
51.2042, -2.5281

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How New Row Farm compares

502nd of 662largest solar farms in the UK register
123rd of 192in South West
0.08%of listed UK solar farms capacity
β‰ˆ 3.9 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.45 MW station would generate roughly 3.9 GWh of electricity in a year, similar to the annual use of about 1,440 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in South West All run by Octopus Investments

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Developer / operator
Lightsource Renewable Energy
Planning authority
Somerset
Planning reference
2013/1510
Application submitted
5 August 2013
Permission granted
11 November 2013
Began operating
31 March 2014
Capacity in planning record
3.9 MW
Address
New Row Farm, Yelling Mill Lane, Downside, Shepton Mallet, Somerset, BA4 4JT
REPD reference
2133

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.