Shooters is a 2 MW onshore wind farm in South West England, operated by Ecotricity. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • South West
  • England

Key facts

Installed capacity
2 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
Ecotricity
Region
South West
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
BA3 4LU
Coordinates
51.2544, -2.5834

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Shooters compares

468th of 488largest wind farms in the UK register
16th of 19in South West
0.01%of listed UK wind farms capacity
β‰ˆ 4.6 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 2 MW station would generate roughly 4.6 GWh of electricity in a year, similar to the annual use of about 1,690 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in South West All run by Ecotricity

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Shooters Bottom Wind Park
Developer / operator
Ecotricity
Planning authority
Somerset
Planning reference
116407-000
Application submitted
15 September 2003
Permission granted
18 May 2006
Began operating
16 June 2008
Capacity in planning record
2 MW
Address
Shooters Bottom, Chewton Mendip,, Somerset
REPD reference
3161

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.