Lawrence End Park
Lawrence End Park is a 5 MW solar farm in East of England, England, operated by Lightsource BP. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- East of England
- England
Key facts
- Installed capacity
- 5 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Lightsource BP
- Region
- East of England
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- LU2 8PF
- Coordinates
- 51.8733, -0.3578
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Lawrence End Park compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 5 MW station would generate roughly 4.4 GWh of electricity in a year, similar to the annual use of about 1,620 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in East of England All run by Lightsource BPNearby generating sites
- Clayhill Β· 9.84 MW solar farm15.3 km
- Hermitage Β· 5 MW solar farm15.4 km
- Manor Farm Eggington Β· 4.99 MW solar farm18.3 km
- Church Farm - Slapton Β· 4.98 MW solar farm18.9 km
- Long Meadow Β· 4.12 MW solar farm19.9 km
- Great Seabrook Β· 4.97 MW solar farm20.1 km
- Potters Bar Β· 5 MW solar farm21.1 km
- Biggleswade Β· 20 MW onshore wind farm21.3 km
Also operated by Lightsource BP
Lightsource BP operates 129 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Ld At Lawrence End Park &, Dane Street
- Developer / operator
- Lightsource Renewable Energy
- Planning authority
- Luton
- Planning reference
- 15/00845/1
- Application submitted
- 30 March 2015
- Permission granted
- 26 June 2015
- Construction started
- 13 October 2015
- Began operating
- 19 December 2015
- Capacity in planning record
- 5 MW
- Address
- Land At Lawrence End Park &, Dane Street, To The E Of Birch Spring, Luton, Bedfordshire, Hertfordshire, LU2 8PE
- REPD reference
- 5142
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.