SOLAR Β· OPERATIONAL

Henbury Quarry

Henbury Quarry is a 3.68 MW solar farm in South West England, operated by Lightsource BP. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • South West
  • England
Project stageOperating
  1. PlanningSep 2013 (completed)
  2. ConsentedMay 2014 (completed)
  3. ConstructionDec 2014 (completed)
  4. OperatingMar 2015 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
3.68 MW
Status
Operational
Technology
Solar Β· PV
Operator
Lightsource BP
Region
South West
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
BH21 3QZ
Coordinates
50.7735, -2.0477

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Henbury Quarry compares

546th of 662largest solar farms in the UK register
139th of 192in South West
0.07%of listed UK solar farms capacity
β‰ˆ 3.2 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 3.68 MW station would generate roughly 3.2 GWh of electricity in a year, similar to the annual use of about 1,190 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in South West All run by Lightsource BP

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Developer / operator
Lightsource Renewable Energy
Planning authority
Dorset
Planning reference
3/13/0948/FUL
Application submitted
20 September 2013
Permission granted
28 May 2014
Construction started
1 December 2014
Began operating
31 March 2015
Capacity in planning record
3.9 MW
Address
Land Adj To Henbury Quarry Henbury Plantation Old Market Road Corfe Mullen Wimborne Dorset BH21 3QZ, Dorset, BH21 3QZ
REPD reference
2139

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.