πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
SOLAR Β· OPERATIONAL

Greencroft

Greencroft is a 4.93 MW solar farm in North East England, operated by Anesco. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • North East
  • England
Project stageOperating
  1. PlanningJul 2015 (completed)
  2. ConsentedNov 2015 (completed)
  3. ConstructionOct 2016 (completed)
  4. OperatingDec 2016 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
4.93 MW
Status
Operational
Technology
Solar Β· PV
Operator
Anesco
Region
North East
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
DH9 7XR
Coordinates
54.8518, -1.7320

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Greencroft compares

431st of 662largest solar farms in the UK register
8th of 10in North East
0.09%of listed UK solar farms capacity
β‰ˆ 4.3 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.93 MW station would generate roughly 4.3 GWh of electricity in a year, similar to the annual use of about 1,600 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in North East All run by Anesco

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Green Croft Solar Farm
Developer / operator
Anesco
Planning authority
County Durham
Planning reference
DM/15/02279/FPA
Application submitted
23 July 2015
Permission granted
4 November 2015
Construction started
7 October 2016
Began operating
7 December 2016
Capacity in planning record
5 MW
Address
Land Between Greencroft Indust, Tower Road/Lanchester Road, Greencroft, Stanley, County Durham, County Durham, DH9 7XR
REPD reference
5380

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026