Ellicombe
Ellicombe is a 1.33 MW solar farm in South West England, operated by Octopus Investments. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- South West
- England
Key facts
- Installed capacity
- 1.33 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Octopus Investments
- Region
- South West
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- EX17 5LS
- Coordinates
- 50.8309, -3.7844
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Ellicombe compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 1.33 MW station would generate roughly 1.2 GWh of electricity in a year, similar to the annual use of about 430 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in South West All run by Octopus InvestmentsNearby generating sites
- Sharland Farm Β· 2.77 MW solar farm0.6 km
- Broadgate Β· 1.1 MW solar farm3.9 km
- Den Brook Wind Farm (GB) Β· 18 MW onshore wind farm7.1 km
- Summerlands Β· 0.81 MW solar farm10.6 km
- West Bradley Β· 1.03 MW solar farm17.8 km
- Batsworthy Cross Β· 10 MW onshore wind farm18.6 km
- Molland Farm Β· 5 MW solar farm22.6 km
- Exeter Β· 50 MW open-cycle gas power station22.8 km
Also operated by Octopus Investments
Octopus Investments operates 134 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Ellicombe Farm
- Developer / operator
- Lightsource Renewable Energy
- Planning authority
- Mid Devon
- Planning reference
- 12/01306/MFUL
- Application submitted
- 13 September 2012
- Permission granted
- 13 December 2012
- Construction started
- 4 March 2013
- Began operating
- 18 March 2013
- Capacity in planning record
- 1.4 MW
- Address
- Morchard Road, Crediton, Devon, Devon, EX17 5LS
- REPD reference
- 1442
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.