Grid infrastructure β€Ί Connection queue β€Ί Wind + storage

WIND + STORAGE Β· SPT

Chesters

Chesters is a 80 MW wind + storage project in planning, connecting to the SP Transmission (south Scotland) network at Teviot 400/132kV Substation, with capacity due from October 2033. The connection agreement is held by Queequeg Renewables Ltd.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2033 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-004805
Customer
Queequeg Renewables Ltd
Technology
Energy Storage System, Wind Onshore
Total capacity
80 MW
Change in this agreement
+80 MW
Capacity effective from
29 October 2033
Connection site
Teviot 400/132kV Substation
Transmission owner
SP Transmission (south Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Scoping

Connection site

The connection site could not be placed on the map.

Projects connecting near Teviot Β· Grid map

Other projects at Teviot 400/132kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem