HYDRO AND PUMPED STORAGE · SPTCruachan U3&4 Replacement
Cruachan U3&4 Replacement is a 440 MW hydro and pumped storage project built and connected, connecting to the SP Transmission (south Scotland) network at Cruachan 275kV Substation. The connection agreement is held by Drax Pumped Storage Limited.
Connection details
- NESO project number
- PRO-000113-1
- Customer
- Drax Pumped Storage Limited
- Technology
- Pump Storage
- Total capacity
- 440 MW
- Already connected
- 440 MW
- Connection site
- Cruachan 275kV Substation
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Built
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Other projects at Cruachan 275kV Substation
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem