Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown968461.1 GW in total
In planning968scoping or awaiting consent
Consented or building149closest to connecting
Built212connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

968 projects · page 7 of 20
ProjectCapacityStageConnection siteFrom
Killingholme Energy Park
Solar + storage · Exagen Group Limited
500 MWScoping South Humber Connection Node A 400kV
National Grid (England & Wales)
Oct 2035
Kingsnorth BESS NP
Battery storage · Noriker Power Ltd
500 MWScoping Kingsnorth 400kV Substation
National Grid (England & Wales)
Dec 2030
Kinoulton Solar & BESS
Solar + storage · Greentech Invest UK (16) Limited
500 MWScoping Trent Valley North Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2034
Lincolnshire Energy Park
Solar + storage · Wind 2 Limited
500 MWScoping South Humber Connection Node A 400kV
National Grid (England & Wales)
Oct 2039
Long Buckby Solar/BESS
Solar + storage · Greentech Invest UK (17) Limited
500 MWScoping Derbyshire Connection Node I 400kV Substation
National Grid (England & Wales)
Oct 2037
Long Stratton PV & BESS Station
Solar + storage · East Pye Solar Limited
500 MWScoping Long Stratton 400kV
National Grid (England & Wales)
Oct 2031
Longfield Solar
Solar + storage · Longfield Solar Energy Farm Limited
500 MWScoping Bulls Lodge 400kV Substation
National Grid (England & Wales)
Oct 2028
Ludgershall - Bicester Solar Farm PVDP
Solar + storage · SolarFour Ltd
500 MWScoping Chiltern Connection Node C 400kV Substation
National Grid (England & Wales)
Nov 2038
Manor Farm
Battery storage · Qair Renewables UK Limited
500 MWScoping East Anglia Connection Node E 400kV Substation
National Grid (England & Wales)
Oct 2034
Medway 3 Power Station
Battery storage · Medway Power Limited
500 MWScoping Kingsnorth 400kV Substation
National Grid (England & Wales)
Apr 2032
Melksham
Solar + storage · Lime Down Solar Park Limited
500 MWAwaiting Consents Melksham 400kV Substation
National Grid (England & Wales)
Jul 2030
Monk Fryston
Solar + storage · Light Valley Solar Limited
500 MWScoping Monk Fryston 400kV Substation
National Grid (England & Wales)
Dec 2029
Nant Helen
Solar + storage · Solar Securities Limited
500 MWScoping South Wales West Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
NatPower Connah Quay Green Energy Park
Battery storage · Connahs Quay Energy Limited
500 MWScoping Cheshire Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2037
Oxfordshire Energy Park
Solar + storage · Low Carbon Solar Park 40 Limited
500 MWScoping Chiltern Connection Node D 400kV
National Grid (England & Wales)
Oct 2037
Partridge Farm BESS
Battery storage · Apatura Battery Ltd
500 MWScoping Sellindge 400kV Substation
National Grid (England & Wales)
Oct 2037
Penrhiwdarren Farm
Battery storage · Qair Renewables UK Limited
500 MWScoping Cilfynydd 400kV Substation
National Grid (England & Wales)
Sep 2037
Project Number 4
Solar + storage · Greta IV Limited
500 MWScoping North Anglia Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2034
Project Number 6
Battery storage · Trent BESS II Limited
500 MWScoping Trent Valley South Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2034
Project Number 8
Battery storage · Trent BESS I Limited
500 MWScoping Trent Valley South Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2034
Rosefield
Solar + storage · Rosefield Energyfarm Limited
500 MWAwaiting Consents East Claydon 400kV Substation
National Grid (England & Wales)
Oct 2031
Save Our Planet
Solar + storage · Save Our Planet Energy Limited
500 MWScoping Sussex and Romney Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2037
Somerset Energy Park
Solar + storage · Low Carbon Solar Park 35 Limited
500 MWScoping Gravity 400kV Substation
National Grid (England & Wales)
Oct 2037
Spennymoor Greener Grid Park
Battery storage · Spennymoor Grid Solutions Limited
500 MWScoping Spennymoor 400kV Substation
National Grid (England & Wales)
Oct 2035
Stable Green Energy
Battery storage · Lh Nget Grid Services Limited
500 MWScoping Sussex and Romney Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
Stallingborough PV & BESS Station
Solar + storage · Stallingborough Energy Project Limited
500 MWScoping Grimsby West 400kV Substation
National Grid (England & Wales)
Oct 2034
Sundon Storage
Battery storage · Statera Energy Limited
500 MWScoping Sundon 400kV Substation
National Grid (England & Wales)
Oct 2027
The Clean Future
Solar + storage · The Clean Future Renewables Limited
500 MWScoping Killingholme 400kV Substation
National Grid (England & Wales)
May 2033
The Droves (formerly Swaffham PV & BESS)
Solar + storage · The Droves Solar Farm Limited
500 MWScoping Swaffham 400KV Substation
National Grid (England & Wales)
Oct 2033
Thornton
Solar + storage · Igp Solar 19 Limited
500 MWScoping Thornton 400kV Substation
National Grid (England & Wales)
Oct 2031
Tillbridge Solar
Solar + storage · Tillbridge Solar Limited
500 MWScoping Cottam 400kV Substation
National Grid (England & Wales)
Aug 2028
West Oxfordshire Energy Park
Solar + storage · Low Carbon Solar Park 43 Limited
500 MWScoping Chiltern Connection Node D 400kV
National Grid (England & Wales)
Oct 2037
Wick Moor Drove
Solar + storage · Bsr Applications Limited
500 MWScoping West Country Connection Node D 400kV Substation
National Grid (England & Wales)
Oct 2037
Willington Energy Park
Solar + storage · Brockwell Storage & Solar Limited
500 MWScoping Willington 400kV Substation
National Grid (England & Wales)
Oct 2028
Bradwell Energy Park
Solar + storage · Low Carbon Solar Park 28 Limited
499 MWScoping Rayleigh 400kV Substation
National Grid (England & Wales)
Oct 2032
Burwell GEC (Ethos Green)
Solar + storage · Burwell Green Energy Centre Ltd
480 MWScoping Burwell 400kV Substation
National Grid (England & Wales)
Oct 2032
Bushbury Green Energy Centre
Solar + storage · Bushbury Green Ng Limited
480 MWScoping Bushbury 275kV Substation
National Grid (England & Wales)
Oct 2028
Butlers Energy Project
Solar + storage · Ig Renewables Spv 1 Ltd
480 MWScoping South Anglia Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2034
Daines Green Energy Centre
Solar + storage · Daines Green Ng Limited
480 MWScoping Daines 400kV Substation
National Grid (England & Wales)
Oct 2030
EPL Hampshire
Solar + storage · Epl Newco7 Limited
480 MWScoping Nursling 400kV Substation
National Grid (England & Wales)
Oct 2037
EPL Somerset
Solar + storage · Epl Newco8 Limited
480 MWScoping West Country Connection Node E 400kV Substation
National Grid (England & Wales)
Oct 2037
EPL Suffolk
Solar + storage · Epl Newco9 Limited
480 MWScoping North Anglia Connection Node E 400kV Substation
National Grid (England & Wales)
Oct 2034
Gresham House Rayleigh BESS
Battery storage · Rayleigh Storage Limited
480 MWScoping Rayleigh 400kV Substation
National Grid (England & Wales)
Jun 2028
Melkshem (Cartridge Farm)
Battery storage · Queequeg Renewables Ltd
480 MWAwaiting Consents Melksham 400kV Substation
National Grid (England & Wales)
Oct 2037
Morecambe Offshore Wind Farm
Offshore wind · Morecambe Offshore Windfarm Ltd
480 MWScoping Penwortham 400kV Substation
National Grid (England & Wales)
Jun 2029
Moreton Estate
Solar + storage · Epl Newco5 Limited
480 MWScoping Chickerell B 400kV Substation
National Grid (England & Wales)
Apr 2037
Noventum - Astwood
Solar + storage · Noventum Power Solar 12 Limited
480 MWScoping West Anglia Connection Node C 400kV Substation
National Grid (England & Wales)
Oct 2034
Pamber Farm
Battery storage · Queequeg Renewables Ltd
480 MWAwaiting Consents Bramley
National Grid (England & Wales)
Oct 2037
Pelham GEC (Ethos Green)
Battery storage · Pelham Green Energy Centre Ltd
480 MWAwaiting Consents Pelham 400kV Substation
National Grid (England & Wales)
May 2035
Spalding PV and BESS Station
Solar + storage · ETP UK 1 LTD
480 MWScoping Weston Marsh 400kV Substation
National Grid (England & Wales)
Jul 2033
Page 7 of 20

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.