United States › Grid › Interconnection queues › California

ONSHORE WIND · CAISO

Golden Hills 1 Wind

Golden Hills 1 Wind is a 50.0 MW onshore wind request withdrawn in the CAISO interconnection queue, in Alameda County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2011 (completed)
  2. Withdrawn / abandonedMay 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
708
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Tesla - Keslo 230 KV
Location
Alameda County, California
Technology
Wind: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
31 March 2011
Proposed online date
December 2013
Withdrawn
May 2013

Location

Marker shows the centre of Alameda County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Alameda County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem