United States βΊ Grid βΊ Interconnection queues βΊ Florida
SOLAR Β· SOUTHEASTSolar project 304A, Highlands County
Solar project 304A, Highlands County is a 74.9 MW solar request withdrawn in the Southeast interconnection queue, in Highlands County, Florida, connecting to Duke Energy Florida.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2022 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 304A
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Duke Energy Florida
- Developer
- Duke Energy Florida, LLC - Henscratch Renewable Energy Center
- Connection point (POI)
- Leisure Lakes Substation
- Location
- Highlands County, Florida
- Technology
- Solar: 74.9 MW
- Total requested
- 74.9 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 29 April 2022
- Proposed online date
- May 2024
Location
Marker shows the centre of Highlands County; the queue data does not give exact sites.
Other requests in Highlands County
- Solar project 259, Highlands CountySolar Β· 74.9 MW Β· under construction
- Solar project 258, Highlands CountySolar Β· 74.9 MW Β· under construction
- Battery storage project FC100008, Highlands CountyBattery storage Β· 100 MW Β· in study
- Solar project 478, Highlands CountySolar Β· 74.5 MW Β· in study
- Solar project 149, Highlands CountySolar Β· 45.0 MW Β· built
- Solar project 177, Highlands CountySolar Β· 74.9 MW Β· withdrawn
- Solar project 256, Highlands CountySolar Β· 74.9 MW Β· withdrawn
- Solar project 257, Highlands CountySolar Β· 74.9 MW Β· withdrawn
- Solar project 138C, Highlands CountySolar Β· 74.9 MW Β· withdrawn
- Solar project FC100005, Highlands CountySolar Β· 74.9 MW Β· withdrawn
- Solar project 175, Highlands CountySolar Β· 74.9 MW Β· withdrawn
- Solar project 304, Highlands CountySolar Β· 74.9 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem