ONSHORE WIND Β· WEST

Onshore wind project G0300, Crook County

Onshore wind project G0300, Crook County is a 104 MW onshore wind request withdrawn in the West interconnection queue, in Crook County, Oregon.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2007 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G0300
Grid region
West (non-ISO utilities)
Connection point (POI)
At a point on BPA's Brasada-Harney 115 kV transmission line
Location
Crook County, Oregon
Technology
Wind: 104 MW
Total requested
104 MW
Service type
Energy only (ERIS)
Study phase
Facility Study
Queue status
Withdrawn
Entered queue
18 December 2007
Proposed online date
October 2010

Location

Marker shows the centre of Crook County; the queue data does not give exact sites.