πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New Mexico

SOLAR + STORAGE Β· WEST

Solar + storage project IA-PNM-2019-09, Santa Fe County

Solar + storage project IA-PNM-2019-09, Santa Fe County is a 60.0 MW solar + storage request withdrawn in the West interconnection queue, in Santa Fe County, New Mexico, connecting to Public Service Company of New Mexico.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandonedMay 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IA-PNM-2019-09
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company of New Mexico
Connection point (POI)
Near Arriba Substation
Location
Santa Fe County, New Mexico
Technology
Solar: 60.0 MW Β· Battery
Total requested
60.0 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
22 April 2019
Proposed online date
December 2022
Withdrawn
May 2023

Location

Marker shows the centre of Santa Fe County; the queue data does not give exact sites.

Power plants in New Mexico Β· Transmission lines in New Mexico

Other requests in Santa Fe County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem