ONSHORE WIND Β· SPP

Onshore wind project GEN-2018-120, Nemaha County

Onshore wind project GEN-2018-120, Nemaha County is a 200 MW onshore wind request withdrawn in the SPP interconnection queue, in Nemaha County, Kansas, connecting to WERE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2018 (completed)
  2. Withdrawn / abandonedDec 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2018-120
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WERE
Connection point (POI)
Kelly 161kV Substation
Location
Nemaha County, Kansas
Technology
Wind: 200 MW
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
21 November 2018
Proposed online date
December 2027
Withdrawn
December 2022

Location

Marker shows the centre of Nemaha County; the queue data does not give exact sites.

Power plants in Kansas Β· Transmission lines in Kansas

Other requests in Nemaha County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem