πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Kansas

ONSHORE WIND Β· SPP

Onshore wind project GEN-2016-170, Nemaha County

Onshore wind project GEN-2016-170, Nemaha County is a 100 MW onshore wind request withdrawn in the SPP interconnection queue, in Nemaha County, Kansas, connecting to WERE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2016 (completed)
  2. Withdrawn / abandonedApr 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2016-170
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WERE
Connection point (POI)
Kelly 115 kV Substation
Location
Nemaha County, Kansas
Technology
Wind: 100 MW
Total requested
100 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
21 November 2016
Proposed online date
December 2019
Withdrawn
April 2017

Location

Marker shows the centre of Nemaha County; the queue data does not give exact sites.

Power plants in Kansas Β· Transmission lines in Kansas

Other requests in Nemaha County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem