Onshore wind project GEN-2016-150, Nemaha County

Onshore wind project GEN-2016-150, Nemaha County is a 302 MW onshore wind request built and operating in the SPP interconnection queue, in Nemaha County, Kansas, connecting to WERE.

Queue statusOperating
  1. PlanningQueued Nov 2016 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2023 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2016-150
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WERE
Connection point (POI)
Stranger Creek 345kV
Location
Nemaha County, Kansas
Technology
Wind: 302 MW
Total requested
302 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue status
Operational
Entered queue
30 November 2016
Proposed online date
December 2023
Came online
December 2023

Location

Marker shows the centre of Nemaha County; the queue data does not give exact sites.