United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

SOLAR Β· PJM

Solar project V4-035, Montgomery County

Solar project V4-035, Montgomery County is a 1.5 MW solar request withdrawn in the PJM interconnection queue, in Montgomery County, Ohio, connecting to Dayton.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2009 (completed)
  2. Withdrawn / abandonedJan 2010 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
V4-035
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dayton
Connection point (POI)
Yankee 12.5kV
Location
Montgomery County, Ohio
Technology
Solar: 1.5 MW
Total requested
1.5 MW
Service type
Energy only (ERIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
14 December 2009
Proposed online date
April 2010
Withdrawn
January 2010

Location

Marker shows the centre of Montgomery County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Montgomery County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem