ONSHORE WIND Β· MISO

Onshore wind project H030, Tuscola County

Onshore wind project H030, Tuscola County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Tuscola County, Michigan.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2009 (completed)
  2. Withdrawn / abandonedDec 2010 (project stopped here)
  3. ConsentedDec 2010 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
H030
Grid region
MISO (Midcontinent)
Connection point (POI)
Atlanta 120kV Substation
Location
Tuscola County, Michigan
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
21 September 2009
Agreement signed
1 December 2010
Proposed online date
October 2014
Withdrawn
December 2010

Location

Marker shows the centre of Tuscola County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Tuscola County