United States βΊ Grid βΊ Interconnection queues βΊ California
GAS Β· CAISOLecu
Lecu is a 24.0 MW gas request built and operating in the CAISO interconnection queue, in San Joaquin County, California, connecting to PGAE.
Request details
- Queue ID
- 945
- Grid region
- CAISO (California)
- Utility / transmission owner
- PGAE
- Connection point (POI)
- Lodi STIG 230 kV Substation
- Location
- San Joaquin County, California
- Technology
- Gas: 24.0 MW
- Total requested
- 24.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Executed
- Queue status
- Operational
- Entered queue
- 30 April 2013
- Proposed online date
- January 2014
- Came online
- April 2017
Location
Marker shows the centre of San Joaquin County; the queue data does not give exact sites.
Power plants in California Β· Transmission lines in California
Other requests in San Joaquin County
- Potentia-ViridiOther Β· 1,225 MW Β· agreement signed
- PresidioSolar + storage Β· 713 MW Β· agreement signed
- Alta Casa StorageBattery storage Β· 515 MW Β· agreement signed
- Pathfinder StorageBattery storage Β· 268 MW Β· agreement signed
- Zeus BESSBattery storage Β· 214 MW Β· agreement signed
- Tracy Combined-Cycle Power PlantGas Β· 185 MW Β· agreement signed
- Denali Energy StorageBattery storage Β· 102 MW Β· agreement signed
- Noosa Energy StorageBattery storage Β· 99.0 MW Β· agreement signed
- Dove CoveBattery storage Β· 514 MW Β· in study
- Northeast Central ValleyBattery storage Β· 365 MW Β· in study
- Zeitgeist K Energy CenterBattery storage Β· 258 MW Β· in study
- Zinfandel Storage CenterBattery storage Β· 154 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem