BATTERY STORAGE · CAISO

North Central Valley

North Central Valley is a 132 MW battery storage request built and operating in the CAISO interconnection queue, in San Joaquin County, California, connecting to PGAE.

Queue statusOperating
  1. PlanningQueued Apr 2015 (completed)
  2. ConsentedJul 2017 (completed)
  3. Construction (completed)
  4. OperatingAug 2023 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
1109
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Belotta 115 kV
Location
San Joaquin County, California
Technology
Battery: 132 MW
Total requested
132 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
30 April 2015
Agreement signed
25 July 2017
Proposed online date
June 2021
Came online
August 2023

Location

Marker shows the centre of San Joaquin County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Joaquin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem