SOLAR + STORAGE · CAISO

Jacumba Ranch

Jacumba Ranch is a 60.3 MW solar + storage request withdrawn in the CAISO interconnection queue, in San Diego County, California, connecting to SDGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2015 (completed)
  2. Withdrawn / abandonedAug 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1174
Grid region
CAISO (California)
Utility / transmission owner
SDGE
Connection point (POI)
East County Substation 138 kV
Location
San Diego County, California
Technology
Solar: 50.3 MW · Battery: 10.0 MW
Total requested
60.3 MW
Service type
Energy only (ERIS)
Study phase
In Progress
Queue status
Withdrawn
Entered queue
30 April 2015
Proposed online date
June 2021
Withdrawn
August 2019

Location

Marker shows the centre of San Diego County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Diego County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem