ONSHORE WIND · SPP

Onshore wind project GEN-2015-089, Bon Homme County

Onshore wind project GEN-2015-089, Bon Homme County is a 200 MW onshore wind request built and operating in the SPP interconnection queue, in Bon Homme County, South Dakota, connecting to WAPA.

Queue statusOperating
  1. PlanningQueued Oct 2015 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingApr 2020 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2015-089
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WAPA
Connection point (POI)
Utica 230 kV Substation
Location
Bon Homme County, South Dakota
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue status
Operational
Entered queue
13 October 2015
Proposed online date
April 2020
Came online
April 2020

Location

Marker shows the centre of Bon Homme County; the queue data does not give exact sites.

Power plants in South Dakota · Transmission lines in South Dakota

Other requests in Bon Homme County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem