United States › Grid › Interconnection queues › South Dakota
ONSHORE WIND · SPPOnshore wind project GEN-2015-089, Bon Homme County
Onshore wind project GEN-2015-089, Bon Homme County is a 200 MW onshore wind request built and operating in the SPP interconnection queue, in Bon Homme County, South Dakota, connecting to WAPA.
Request details
- Queue ID
- GEN-2015-089
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- WAPA
- Connection point (POI)
- Utica 230 kV Substation
- Location
- Bon Homme County, South Dakota
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA FULLY EXECUTED/COMMERCIAL OPERATION
- Queue status
- Operational
- Entered queue
- 13 October 2015
- Proposed online date
- April 2020
- Came online
- April 2020
Location
Marker shows the centre of Bon Homme County; the queue data does not give exact sites.
Power plants in South Dakota · Transmission lines in South Dakota
Other requests in Bon Homme County
- Onshore wind project GI-1501, Bon Homme CountyOnshore wind · 200 MW · in study
- Onshore wind project 165, Bon Homme CountyOnshore wind · 130 MW · built
- Onshore wind project GI-0920a, Bon Homme CountyOnshore wind · 80.0 MW · built
- Onshore wind project GI-1216, Bon Homme CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project GI-1306, Bon Homme CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project 109, Bon Homme CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project GI-0920, Bon Homme CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project GI-0919, Bon Homme CountyOnshore wind · 125 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem