🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New York

SOLAR + STORAGE · NYISO

Sunwine Solar

Sunwine Solar is a 50.0 MW solar + storage request withdrawn in the NYISO interconnection queue, in Chautauqua County, New York.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2021 (completed)
  2. Withdrawn / abandonedOct 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1224
Grid region
NYISO (New York)
Developer
Northland Power U.S. Projects
Connection point (POI)
Westfield Electric 115kV
Location
Chautauqua County, New York
Technology
Solar: 50.0 MW · Battery
Total requested
50.0 MW
Queue status
Withdrawn
Entered queue
28 July 2021
Withdrawn
October 2021

Location

Marker shows the centre of Chautauqua County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Chautauqua County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem