EcoGrove WF (67 WT) is a 100 MW onshore wind request built and operating in the PJM interconnection queue, in Jo Daviess County, Illinois, connecting to ComEd.
Request details
- Queue ID
- P46
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ComEd
- Connection point (POI)
- Lena 138kV
- Location
- Jo Daviess County, Illinois
- Technology
- Wind: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 23 January 2006
- Agreement signed
- 5 February 2009
- Proposed online date
- March 2009
- Came online
- October 2007
Location
Marker shows the centre of Jo Daviess County; the queue data does not give exact sites.
Other requests in Jo Daviess County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem