United States › Grid › Interconnection queues › Massachusetts

SOLAR + STORAGE · ISO-NE

Solar plus Battery

Solar plus Battery is a 1.0 MW solar + storage request withdrawn in the ISO-NE interconnection queue, in Worcester County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2022 (completed)
  2. Withdrawn / abandonedSep 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1224
Grid region
ISO-NE (New England)
Connection point (POI)
National Grid MA 13.8 kV, Whitins Pond 320W5
Location
Worcester County, Massachusetts
Technology
Solar: 1.0 MW · Battery
Total requested
1.0 MW
Service type
Network resource (NRIS)
Study phase
In Progress
Queue status
Withdrawn
Entered queue
25 January 2022
Proposed online date
April 2022
Withdrawn
September 2022

Location

Marker shows the centre of Worcester County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Worcester County